ABB Completes Dyno Nobel Moranbah Plant Overhaul

ABB finished an electrical maintenance and modernisation programme during the plant's 2025 major shutdown.

Updated on Nov. 25, 2026 in Industry

Bold flat-color vector editorial illustration of a row of slate-grey industrial switchgear cabinets, one with a mustard protection relay module, representing electrical upgrades at an industrial plant.
ABB completed an electrical maintenance and modernisation programme at Dyno Nobel's Moranbah plant in Queensland during the site's 2025 major shutdown, finishing on schedule and within budget. AI Illustration. Upload story photo >

ABB completed an electrical maintenance and modernisation programme at Dyno Nobel's Moranbah plant in Queensland, carried out during the site's 2025 major shutdown. The turnaround was finished on schedule and within budget, avoiding a projected cost overrun.

Why it matters

The work upgraded the plant's electrical systems and added digital monitoring capabilities intended to support a shift towards proactive maintenance. The project also shows how a large shutdown can be delivered without safety incidents across a heavily staffed site.

The turnaround lasted just over 45 days with nearly 900 personnel on site at peak, and included more than 100 MStart modules and 30 MNS iS motor control centre modules. The project recorded 185,326 man-hours with zero safety incidents, though the final cost figure was not disclosed.

The players

ABB

ABB is a global industrial technology company that supplies electrification, automation and robotics products and services.

Dyno Nobel

Dyno Nobel is an Australian-based explosives and mining services company that operates the Moranbah plant.

The details

The work included lifecycle maintenance, digital monitoring capabilities and resilience planning. ABB installed MNS iS low-voltage digital switchgear, replaced older relays with REF615 protection relays, and completed detailed inspections of the site's low- and medium-voltage switchgear. Discrepancies between site panels and engineering drawings were addressed during execution.

Timeline

  1. 2025: Major shutdown turnaround at the Moranbah plant, lasting just over 45 days.

  2. Every four years: Recurring plant turnaround schedule.

Market Landscape

The project reflects a wider move by industrial operators to modernise ageing electrical infrastructure during scheduled shutdowns rather than through separate interventions. Digital switchgear such as MNS iS is becoming a standard means of adding monitoring to plants like the Moranbah facility.

For operators, the shutdown shows that plant upgrades can be scheduled around the regular four-year turnaround cycle. The added digital monitoring is intended to shift maintenance towards a proactive approach rather than reacting to failures.

The takeaway

Scheduling electrical upgrades within planned shutdowns can reduce disruption and cost overruns. Adding digital monitoring during such work can support a move from reactive to proactive maintenance.