APA Starts 104MWh Solar-Plus-Storage Project

The Sybella Creek project in Queensland will be built by UGL under an engineering, procurement and construction contract.

Updated on Nov. 24, 2026 in Energy

Wide photograph of rows of dark solar panels and plain steel battery enclosures across flat red-brown outback terrain under a clear sky.
APA has started work on a 104MWh solar-plus-storage project at Sybella Creek in Queensland, committing AU$259 million under a supply agreement with Ernest Henry Mining. AI Illustration. Upload story photo >

Live Poll

Do you think your local energy costs are getting better or worse?

APA has started work on a 104MWh solar-plus-storage project at Sybella Creek, committing AU$259 million under a supply agreement with Ernest Henry Mining that runs until mid-2046. UGL has been appointed to provide engineering, procurement and construction services for the project.

Why it matters

The North West Minerals Province has long relied on isolated diesel and gas generation because it has no connection to the National Electricity Market. Projects like Sybella Creek offer an alternative energy supply for mining operations in Queensland's remote north-west.

The AU$259 million commitment is a supply-agreement value under a contract running until mid-2046, and the 104MWh capacity is set against the Port Hedland project's 36.7MWh battery for scale. The completion date and operational performance of the project have not been disclosed.

The players

APA Group

APA Group is one of Australia's largest energy infrastructure companies, operating gas pipelines and increasingly investing in renewable energy and storage assets.

UGL

UGL is an Australian engineering and services contractor, owned by CIMIC Group, that delivers large solar and battery energy storage projects across the region.

Ernest Henry Mining

Ernest Henry Mining is a copper mine in north-west Queensland and the counterparty to the supply agreement with APA for the Sybella Creek project.

The details

APA took a final investment decision on Sybella Creek in August, and UGL, owned by CIMIC Group, was appointed in September as engineering contractor. UGL previously worked with APA on the Port Hedland project in Western Australia, and the project is UGL's 16th solar and 12th battery energy storage system project.

Timeline

  1. August 2026: APA took the final investment decision on Sybella Creek.

  2. September 2026: UGL was appointed as the engineering, procurement and construction contractor.

  3. Mid-2046: The supply agreement with Ernest Henry Mining expires.

Roadmap

The Sybella Creek project repeats the APA and UGL partnership model first used at Port Hedland in Western Australia, applying it to an off-grid mining region. It extends that approach to Queensland's North West Minerals Province, which has no connection to the National Electricity Market.

For mining operators in the North West Minerals Province, a solar-plus-storage supply could reduce reliance on isolated diesel and gas generation. Residents and businesses in the region are not directly affected by the contract itself.

The takeaway

Long-term supply contracts such as the one running to mid-2046 give remote energy projects the revenue certainty needed to secure financing. Remote mining regions may increasingly depend on storage-backed renewables rather than diesel.

Further reading

For more on the state's power plans, see Energy coverage across Queensland.

Source note: This article includes information reported by Energy Storage News.