29Metals Gains Approval to Restart Capricorn Copper
Preliminary approval for a major environmental authority amendment paves the way for the Queensland copper mine to resume operations.
Updated on Nov. 16, 2026 in Environmental

29Metals has received preliminary approval for a major amendment to its Capricorn Copper environmental authority, enabling construction of tailings storage facility TSF 3 and related infrastructure. The approval, issued by the Queensland Department of Environment, Tourism, Science and Innovation, is a step toward restarting operations suspended in March 2024.
Why it matters
Operations were halted after an extended period of rainfall caused water to accumulate on site, and the mine was still recovering from a deluge in 2023 when the suspension occurred. Surface water inventory has since been reduced by 2.3 GL, the equivalent of 900 Olympic-size swimming pools, and the company says the mine has the potential to more than double its annual copper production.
Surface water inventory at Capricorn Copper has fallen by 2.3 GL since operations were suspended in March 2024, equivalent to 900 Olympic-size swimming pools. The restart definitive feasibility study, which incorporates TSF 3 and a water treatment plant, is due by the end of 2026, and the funding route for the restart has not yet been settled.
The players
29Metals
A mining company that owns and operates the Capricorn Copper mine in North-West Queensland and is seeking to restart its operations.
Queensland Department of Environment, Tourism, Science and Innovation
The Queensland state government department that issued the preliminary environmental authority approval for the Capricorn Copper amendment.
The details
29Metals plans to tender for construction of the new tailings storage facility and water treatment plant in the new year. A response to the Federal Department of Climate Change, Energy, the Environment and Water's request for information on TSF 3 is expected before the end of the year, and the approval followed extensive engagement with the local community and the Queensland Government.
Timeline
March 2024: Capricorn Copper operations suspended after water accumulated on site.
2023: The mine was recovering from a deluge when the suspension occurred.
16 November 2026: Preliminary environmental authority approval announced.
End of 2026: Restart definitive feasibility study due for completion.
New year (2027): 29Metals plans to tender for tailings facility and water treatment plant construction.
Big Picture
The preliminary approval is a further step in the Queensland environmental authority process, which governs how a mine like Capricorn Copper manages its tailings and site water. The move follows three years of work to improve site water management after the 2023 deluge.
Queensland residents in the North-West region may see the restart of a major local employer and copper producer as the mine resumes operations. The approval also means the site's water inventory and tailings management will be under closer state oversight during the rebuild.
The takeaway
The mine's restart depends on a sequence of approvals, feasibility studies and funding decisions still to come, so the timeline may shift. Readers tracking Queensland's mining sector should watch the end-of-2026 feasibility study and the planned tender in the new year.
What happens next
A response to the Federal Department of Climate Change, Energy, the Environment and Water's request for information on TSF 3 is expected before the end of 2026, and the restart definitive feasibility study is due by the end of 2026. The tender for tailings facility and water treatment plant construction is planned for the new year.