Contractors Complete Bridge Piling at Victoria Pass
Work on a new bridge over Mitchell's Causeway advances while the Great Western Highway remains closed at Victoria Pass.
Updated on Nov. 21, 2026 in Industry

Live Poll
Do you think your area's major road repairs are being handled well?
Contractors have completed driving 54 major piles, each up to 20 metres long, into bedrock for a new bridge over Mitchell's Causeway. The Great Western Highway at Victoria Pass has been closed since early March 2026 after engineers found serious cracking and ground movement in the stone causeway.
Why it matters
The closure has forced up to 12,000 vehicles a day onto detours, including a 25-minute route via Darling Causeway and Chifley Road. The $200 million project is jointly funded by the state and Commonwealth governments, with the NSW Government spending an extra $50 million on upgrading the detour routes.
Contractors have driven 54 piles of up to 20 metres each for the bridge, while more than 50,000 tonnes of asphalt has been laid on detour routes for up to 12,000 daily vehicles. The final timing for the third eastbound lane remains unconfirmed.
The players
Jenny Aitchison
Jenny Aitchison is a New South Wales public official whose office is connected to the state's transport and road infrastructure announcements.
Catherine King
Catherine King is the federal minister whose portfolio covers infrastructure, contributing Commonwealth funding to the Victoria Pass project.
Transport for NSW
Transport for NSW is the New South Wales state government agency responsible for the state's transport network, including the Great Western Highway.
The details
The new bridge will use a reinforced concrete road deck built above the stone causeway, with the third eastbound lane sitting on 14 piles topped with 14 columns. Over the next six weeks, crews will build a five-metre-high retaining wall to support a piling rig for that lane.
Timeline
Early March 2026: Great Western Highway closed at Victoria Pass after cracking was found in the causeway.
November 2026: Piling for the new bridge completed on time.
Next six weeks: Construction starts on the third lane retaining wall.
April to June 2027: Victoria Pass section expected to reopen to two lanes.
Market Landscape
The $200 million Victoria Pass project is part of the joint state and Commonwealth funding commitment to upgrade the Great Western Highway through the Blue Mountains. It reflects a pattern of major road rebuilds in the region that rely on coordinated federal and state investment.
Drivers crossing the Blue Mountains face detours of about 25 minutes via Darling Causeway and Chifley Road while the highway is closed. Motorists should plan extra travel time until the Victoria Pass section reopens.
The takeaway
Major road closures can ripple through daily commutes for months, so checking detour routes before travelling helps. The Victoria Pass reopening is currently scheduled for the April to June 2027 window.
What happens next
The Victoria Pass section of the Great Western Highway is expected to reopen to two lanes between April and June 2027.
Further reading
Explore more Construction stories covering major road and bridge projects across New South Wales.
Source note: This article includes information reported by The Sydney Morning Herald.