Batteries Lead 8.4 GW of New NEM Capacity

Battery storage supplied most of the new generation that reached full output in Australia's National Electricity Market since December 2025.

Updated on Nov. 22, 2026 in Energy

Batteries Lead 8.4 GW of New NEM Capacity

Live Poll

Do you trust Australia's grid to keep the lights on during summer heatwaves?

More than 30 new projects totalling 8.4 GW have reached full output in the National Electricity Market since December 2025, according to the Australian Energy Market Operator (AEMO). Batteries supplied 5.3 GW of that new capacity, with solar, wind, gas and hybrid projects adding the remainder.

Why it matters

The shift towards batteries is changing how the grid meets evening demand, with batteries overtaking gas at the evening peak in the third quarter. AEMO's summer outlook warns of elevated risk periods ahead, so the pace of new storage will shape how reliably power is supplied during heatwaves across the country.

Grid-scale battery storage in the NEM exceeded 10 GW / 23 GWh by the end of September, counting units still in commissioning. AEMO has not given the batteries' energy capacity in MWh in its release or outlook.

The players

Australian Energy Market Operator

The Australian Energy Market Operator runs the National Electricity Market and the power system across eastern and southern Australia, and publishes the capacity and reliability assessments on which this story is based.

Michael Gatt

Michael Gatt is the federal Minister for Energy in the Australian Government, responsible for national energy policy and the grid transition.

The details

Solar added 1.1 GW, wind 0.7 GW, gas-fired generation 0.7 GW and hybrid solar and battery projects 0.5 GW. Separately, three batteries totalling 600 MW reached full output in Western Australia's Wholesale Electricity Market, and Project EnergyConnect Stage 2 was energised in early November.

Timeline

  1. December 2025: Period in which more than 30 new projects reached full output in the NEM begins.

  2. First half of 2026: 2.3 GW / 7.1 GWh of large batteries switched on across Australia.

  3. Early November 2026: Project EnergyConnect Stage 2 energised.

  4. 20 November 2026: AEMO published its summer readiness release.

  5. January 2027: AEMO's loss-of-load study identifies periods of elevated risk in Victoria and South Australia.

Big Picture

The additions follow AEMO's 2026-27 Summer Outlook, which expects a warmer and drier summer than average across most of Australia and flags elevated January 2027 risk in Victoria and South Australia. Batteries now supply most new capacity, so their performance during heatwaves will test whether the storage build-out offsets those risks.

More batteries on the grid means evening power supply depends less on gas, which may ease price pressure during peak periods, though AEMO has not quantified any effect on household bills. Households should watch AEMO's summer readiness advice if heatwaves bring periods of elevated supply risk.

The takeaway

Battery storage is now the largest source of new capacity in the National Electricity Market, but AEMO's risk findings mean its real test will come during the summer heat ahead. Track the capacity updates and the summer readiness advice before assuming supply is secure.

What happens next

AEMO expects heatwaves could set new records for maximum demand in both markets this summer, and its January 2027 risk periods in Victoria and South Australia will show whether the new capacity is enough.

Further reading

For broader context on how storage is reshaping the grid, see Energy coverage.

Source note: This article includes information reported by List.