NextDC Shareholders Reject Remuneration Report
Investors voted against the report after Jemena paused power pole work that delayed the West Footscray data centre expansion.
Updated on Nov. 20, 2026 in Data Centers

Live Poll
Should data centers be allowed to expand in your community despite local opposition?
Shareholders of NextDC rejected the company's remuneration report, with 72 per cent of pre-meeting votes against it. The vote followed October delays to the West Footscray data centre expansion after Jemena paused installation of industrial-sized power poles on local streets.
Why it matters
The remuneration report does not stop senior staff being paid, but it does trigger the possibility of a vote to spill the board. The delays cut hundreds of millions of dollars from NextDC's revenue forecasts for next year, the figure that drove investor anger.
The figure is a pre-meeting shareholder vote tally, with 72 per cent of votes lodged against the remuneration report. The final meeting result and the precise size of the revenue cut from the power pole delays are not included in the available information.
The players
NextDC
NextDC is an Australian data centre operator that runs large facilities in Melbourne and Sydney.
Jemena
Jemena is an Australian energy network business that owns and operates electricity and gas infrastructure across eastern Australia.
Craig Scroggie
Craig Scroggie is the chief executive of NextDC and a prominent figure in Australia's data centre sector.
The details
Resident protests in October prompted Jemena to pause installation of industrial-sized power poles on local streets needed to supply the West Footscray expansion. NextDC announced the pause and resulting project delays the same month, and has since unveiled modest improvements to forecasts it had slashed, while establishing a committee to consult the community.
Timeline
October 2026: Resident protests prompt Jemena to pause power pole installation and NextDC announces delays and forecast cuts.
20 November 2026: NextDC annual general meeting in Sydney, where shareholders vote against the remuneration report.
Big Picture
The dispute reflects how data centre expansion in Melbourne's western suburbs is running into the limits of local electricity network upgrades. Community objections to new power infrastructure are now shaping the timelines and financial outlook of operators like NextDC.
Residents near planned data centre sites may see power infrastructure work on local streets, including the installation of large poles, as projects proceed. Shareholders and investors in NextDC can weigh the company's revenue outlook against the delays now affecting its forecasts.
The takeaway
Large data centre projects depend on local power networks as much as on capital, so delays in grid works can quickly reshape a company's financial outlook. Community consultation over infrastructure is now a material factor for both operators and investors.