TVEL Delivers Fuel for Tianwan Unit 8 in China
Rosatom's fuel division has delivered the initial fuel load for the eighth unit at the Tianwan Nuclear Power Plant.
Updated on Nov. 26, 2026 in Nuclear

TVEL, the fuel division of the Rosatom state corporation, delivered the initial fuel load for unit 8 of the Tianwan Nuclear Power Plant in China. The unit has completed hot functional testing and is being prepared for fuel loading, with commissioning planned for the first quarter of 2027.
Why it matters
The delivery advances Rosatom's construction of VVER-1200 reactors at Chinese sites, with three reactor cores delivered for Tianwan units 7 and 8 and Xudapu unit 3 as of late 2025. It also indicates the project is moving from testing toward operation.
Three VVER-1200 reactor cores have been delivered for Tianwan units 7 and 8 and Xudapu unit 3, with unit 7 connected to the grid in October. The source does not indicate whether unit 8 commissioning will stay on the first-quarter 2027 schedule.
The players
Rosatom
Rosatom is Russia's state nuclear corporation, which oversees nuclear fuel, reactor construction and exports, including the Chinese projects at Tianwan and Xudapu.
TVEL
TVEL is the nuclear fuel division of Rosatom, responsible for supplying fuel assemblies and reactor cores for Russian-designed plants abroad.
Anton Ivanov
Anton Ivanov is Vice President for Commerce and International Business at JSC TVEL, overseeing the company's commercial and overseas operations.
The details
The unit completed hot functional testing before receiving its initial fuel load, which TVEL delivered on November 26. The nuclear industry's media center reported the status of unit 8 this week, while Anton Ivanov, Vice President for Commerce and International Business at JSC TVEL, is the company's commercial lead.
Timeline
Late 2025: Three VVER-1200 reactor cores delivered for units 7, 8 and Xudapu unit 3.
October 2026: Tianwan unit 7 connected to the grid.
November 26, 2026: TVEL delivered the initial fuel load for unit 8.
December 2026: Commissioning of Xudapu unit 3 is scheduled.
First quarter of 2027: Commissioning of Tianwan unit 8 is scheduled.
Big Picture
The delivery extends Rosatom's VVER-1200 export program in China, which has placed reactor cores at Tianwan units 7 and 8 and Xudapu unit 3. Unit 8 now moves from construction toward commissioning, with the first quarter of 2027 as the stated target.
The reactor projects at Tianwan and Xudapu are a step toward expanded nuclear electricity generation in China, with commissioning timelines set for the coming months. Timelines may shift, so the stated schedules should be read as company targets.
The takeaway
Large nuclear builds move in stages, from core delivery to testing, fuel loading and grid connection, so each milestone is worth tracking against its published schedule. The next checkpoint for this project is commissioning of Xudapu unit 3 in December.
What happens next
Commissioning of Xudapu unit 3 is scheduled for December, and commissioning of Tianwan unit 8 is set for the first quarter of 2027.
Further reading
Explore more reporting on Nuclear developments across major reactor projects.
Source note: This article includes information reported by Interfax.