South Africa Weighs 10000MW Nuclear Expansion
Government is assessing a wider nuclear programme after Eskom submitted a feasibility report for a 5200MW build.
Updated on Nov. 27, 2026 in Science

Live Poll
Should South Africa build a large new nuclear programme despite its cost?
South Africa's government is considering a 10000MW nuclear expansion to rebuild its nuclear industry. The Integrated Resource Plan 2025 provides for 5200MW of new nuclear generation by 2039, and Eskom has submitted a feasibility report for that programme.
Why it matters
Government wants to restore nuclear fuel-cycle capabilities to strengthen energy sovereignty and support industrialisation, localisation, mineral beneficiation, skills development and job creation. Modelling anticipates electricity demand rising substantially by 2040.
The 5200MW figure is set by the Integrated Resource Plan 2025 and sits within a wider 10000MW programme under assessment, measured against net generation of about 225 terawatt hours. Whether the wider programme proceeds, and at what cost, has not been settled.
The players
Eskom
Eskom is South Africa's state-owned electricity utility, responsible for most of the country's power generation and transmission.
Kgosientsho Ramokgopa
Kgosientsho Ramokgopa is a South African public official who has led the government's electricity and energy portfolio on power-sector planning.
The details
The Department is preparing a proposed section 34 determination for public participation, and government plans to restore capabilities across the nuclear fuel cycle, from uranium conversion and enrichment to fuel fabrication, power generation and waste management. Eskom has proposed a site at Duynefontein, near the existing Koeberg station.
Timeline
2023: Peak load shedding occurred in South Africa.
2026: Curtailment replaced peak load shedding.
Before June 2027: The Minister intends to publish the proposed section 34 determination.
2039: Target year for 5200MW of new nuclear generation.
2040: Modelled year for rising electricity demand.
Big Picture
The proposal extends the Integrated Resource Plan 2025, which provides for 5200MW of new nuclear generation by 2039, toward a wider 10000MW programme. It follows a period in which South Africa moved from peak load shedding in 2023 to curtailment in 2026.
Electricity supply is expected to tighten as demand rises toward 2040, so the pace of new generation affects reliability for households and businesses. The first new nuclear power is about a decade away, meaning near-term supply relies on existing capacity.
The takeaway
South Africa's nuclear choice ties directly to long-term electricity reliability and industrial policy. Readers should track the forthcoming public participation process on the proposed determination.
What happens next
The Minister intends to publish the proposed section 34 determination for public participation before June 2027, and the first electrons from new nuclear are about a decade away.
Further reading
Explore more on the country's energy plans in our Nuclear section.
Source note: This article includes information reported by Cape Times.