EMC Subsea Cable Installation Begins in Marseille
The $1 billion EMC project will link Europe with Saudi Arabia, India and Singapore through Greece, Cyprus, Israel and Jordan.
Updated on Nov. 26, 2026 in Telecommunications

Installation of the EMC subsea fibre-optic cable system began in Marseille, carried out by the cable-laying vessel Ile d'Yeu operated by Alcatel Submarine Networks. The first phase, EMC-West, has a budget of $600 million and is scheduled for completion in late 2028 or early 2029.
Why it matters
EMC is designed to provide an alternative data transmission route between Europe and Asia that bypasses Egypt. It is also the first subsea cable system in the Eastern Mediterranean financed on the basis of projected revenues.
The EMC system is a subsea fibre-optic network financed with a €340 million syndicated loan for its first phase, which was secured in 2024 from National Bank of Greece, Piraeus Bank, Alpha Bank and Saudi Arabia's Bank Aljazira. Technical capacity figures and route specifications beyond the stated connection points have not been disclosed in the source material.
The players
Saudi Telecom (STC)
Saudi Telecom is the largest telecommunications company in Saudi Arabia, and through its subsidiary Center3 it holds a 72% stake in EMC Subsea Cable Co. Ltd.
PPC
PPC is a Greek electricity utility that has been expanding its telecommunications activities beyond Greece and holds a 25% stake in EMC Subsea Cable Co. Ltd.
Alcatel Submarine Networks
Alcatel Submarine Networks is a global manufacturer and operator of submarine cable systems, and it operates the cable-laying vessel Ile d'Yeu used in the EMC project.
The details
Following shore landing of the first cable section, the cable will be laid on the Mediterranean seabed. The Greek route is part of a network with two cables originating in Marseille and Genoa, with connection points planned in Crete and Athens. The project extends to India and Singapore in the second phase, EMC-East.
Timeline
May 2024: Implementation of the EMC project began.
2024: A €340 million syndicated loan was secured to finance the first phase.
November 25, 2026: Installation of the EMC cable began in Marseille on a Wednesday.
Late 2028 or early 2029: EMC-West is scheduled for completion.
Roadmap
The EMC project is the first subsea cable system in the Eastern Mediterranean financed on the basis of projected revenues, marking a financing model departure for the region. It creates an alternative route between Europe and Asia that avoids Egypt, extending the network of Mediterranean corridors that have historically routed traffic through Egyptian infrastructure.
The EMC cable is intended to provide an alternative data transmission path between Europe and Asia, which could affect the routing and performance of international internet traffic for users in connected regions. Consumer-facing effects such as pricing or service availability are not addressed in the source material.
The takeaway
Undersea cable projects like EMC show how large telecommunications infrastructure can be financed through projected revenues rather than public funding alone. Readers tracking international data routing should watch the EMC-West completion timeline in 2028 and 2029.
What happens next
EMC-West is scheduled for completion in late 2028 or early 2029, at which point the first phase of the cable network is expected to be operational.
Further reading
Explore more Telecommunications coverage for context on undersea cable networks and international data routes.
Source note: This article includes information reported by Η Ναυτεμπορική.