IKM Testing Finishes Sean Papa Conductor Cutting Early
The offshore campaign, carried out with ONE-Dyas and Swift Drilling, was completed in eight days against a 14-day plan.
Updated on Nov. 25, 2026 in Oil and Gas

IKM Testing completed a conductor cutting and retrieval campaign at the Sean Papa platform in the North Sea six days ahead of schedule. The work was carried out alongside field operator ONE-Dyas and rig operator Swift Drilling.
Why it matters
The campaign is an example of verification technology cutting offshore decommissioning time and cost. Estimated savings for the client reached $1.96 million (£1.5 million), a figure that may interest operators planning similar platform removals.
The campaign finished in 8 days against a 14-day original plan, and the estimated $1.96 million (£1.5 million) in client savings is a contractor projection, not an audited figure. The source does not explain the basis of that estimate.
The players
IKM Testing
IKM Testing is a provider of inspection, testing and cutting services to the offshore energy industry.
ONE-Dyas
ONE-Dyas is an operator of offshore gas fields in the North Sea.
Swift Drilling
Swift Drilling is a drilling contractor that served as rig operator for the campaign.
The details
IKM Testing developed a conductor cutting verification system with specialist supplier ANT. Patented external sensors detect when the outermost conductor has been fully cut and send a result to a control system that shows a green indicator. The system was deployed with IKM Testing's abrasive waterjet cutting and conductor retrieval equipment, and the Sean Papa job was its third commercial deployment and first for ONE-Dyas.
Timeline
The Sean Papa campaign was completed six days ahead of schedule, with the report published November 25, 2026.
Earlier IKM Testing work for ONE-Dyas took place at the Sean Romeo platform; the source does not give a date for it.
Market Landscape
The campaign extends abrasive waterjet conductor cutting, which is widely used in North Sea platform decommissioning, by adding external sensors that confirm when a cut is complete. The approach could influence how contractors compete on decommissioning speed and cost as operators retire ageing platforms.
For operators and contractors planning platform removals, verified cut detection may shorten offshore schedules and reduce the number of cutting passes. Those effects would show up in project budgets and timelines rather than in consumer prices.
The takeaway
Verification technology that confirms a cut is complete can reduce wasted offshore time during decommissioning. Operators weighing removal options may find that independent cut confirmation is worth assessing against their own project costs.
Further reading
For related coverage, see Oil and Gas reporting on offshore operations and platform decommissioning.
Source note: This article includes information reported by Offshore Engineer.