Allseas Issues Letter for Statfjord A Topside Recycling

Aker Solutions would dismantle and recycle the roughly 50,000-tonne Equinor platform top structure at its Stord facility in western Norway.

Updated on Nov. 17, 2026 in Oil and Gas

Steel offshore platform top structure being lifted by a heavy-lift crane vessel over grey North Sea water, with a distant shoreline under overcast sky.
Allseas has issued Aker Solutions a letter of intent to dismantle and recycle the topside of Equinor's Statfjord A platform, a contract valued at NOK 500 million to NOK 1.5 billion. AI Illustration. Upload story photo >

Allseas has issued Aker Solutions a letter of intent to dismantle and recycle the topside of Equinor's Statfjord A platform in the North Sea. The contract is valued at between NOK 500 million and NOK 1.5 billion ($52 million to $155 million) and is classified as sizeable by Aker Solutions.

Why it matters

The project marks a step in the decommissioning of aging North Sea oil infrastructure, a process that is becoming a growing part of industry activity. For readers following the energy sector, it shows how removal and recycling work is being contracted as older platforms reach the end of their operating lives.

The letter of intent values the contract at NOK 500 million to NOK 1.5 billion ($52 million to $155 million), with the 50,000-tonne structure to be lifted in one operation. Final contract award is still subject to completion, and the projected 2029 to 2031 arrival window has not been confirmed.

The players

Equinor

Equinor is a Norwegian state-influenced energy company that operates oil and gas fields across the North Sea and beyond.

Allseas

Allseas is a Swiss-based offshore construction and heavy-lift contractor known for operating the Pioneering Spirit vessel.

Aker Solutions

Aker Solutions is a Norwegian engineering and technology company that provides services for the offshore energy industry.

The details

Allseas will remove the topside from the concrete gravity-based foundation using the heavy-lift vessel Pioneering Spirit in a single operation. The agreement covers preparatory work, reception, dismantling and recycling, with dismantling taking place at Aker Solutions' Stord facility in western Norway.

Timeline

  1. November 1979: Statfjord A began production.

  2. 2019: Equinor and Allseas first announced arrangements for removing and recycling the structure.

  3. 2022: The Gyda topside was delivered to Stord for recycling.

  4. Fourth quarter of 2026: Aker Solutions expects to book the Statfjord A contract.

  5. 2029 to 2031: The Statfjord A topside is expected to arrive at Stord.

Industry Trajectory

The Statfjord A letter of intent follows the 2019 Equinor and Allseas announcement, moving the removal of this platform top from planned arrangements toward contracting. The Gyda topside delivered to Stord in 2022 shows the same Aker Solutions facility already handling comparable North Sea decommissioning work.

For readers in the energy and engineering sectors, the project signals continued contracting work in North Sea decommissioning through the late 2020s and early 2030s. The roughly 100 personnel expected at peak activity point to job opportunities concentrated around the Stord facility in western Norway.

The takeaway

Removing offshore platforms is a long, multi-year process that begins with contracting well before the structure reaches a recycling yard. Tracking these letters of intent and final awards gives a clearer view of how the North Sea's aging infrastructure will be handled over the coming decade.

What happens next

Aker Solutions expects to book the Statfjord A contract in the fourth quarter of 2026, subject to final award.

Further reading

For more on the sector behind this project, see Oil and Gas coverage.

Source note: This article includes information reported by Splash247.