Olga Completes Brenner Base Tunnel Eastern Bore

The last of nine tunnel boring machines finished excavating the eastern main railway bore of the 55 km Brenner Base Tunnel.

Updated on Nov. 25, 2026 in Transportation

Large steel tunnel boring machine cutterhead breaking through a rock face into a lit tunnel bore, with a grey Alpine mountain range in the distance.
Excavation crews finished boring the eastern main railway tube of the 55 km Brenner Base Tunnel on 24 November, as the final of nine tunnel boring machines broke through at Navis, Austria. AI Illustration. Upload story photo >

Tunnel boring machine Olga broke through at Navis, Austria, on 24 November, completing excavation of the eastern main railway bore of the Brenner Base Tunnel. Olga was the final of nine machines used on the 55 km project.

Why it matters

The breakthrough closes out excavation of the tunnel's main railway bores, a step toward the cross-Alpine rail link between Austria and Italy. However, BBT SE has revised its programme, pushing regular train service targets to 2034 and raising the forecast cost to €11.7 billion.

Olga drove about 7.67 km and Wilma drove 7.45 km of the bores, with the forecast cost rising from €10.5 billion to €11.7 billion. Regular service is now targeted for 2034, two years behind the earlier plan, and BBT SE has not detailed how the added cost will be covered.

The players

BBT SE

BBT SE is the company developing and constructing the Brenner Base Tunnel, the cross-Alpine rail link between Austria and Italy.

The details

Olga, a 10.37 m cutterhead double-shield machine, started on 18 September 2024 from an assembly cavern below St Jodok and passed through several fault zones, including the Jana zone. It broke into the IRIS auxiliary drive, where four machines meet, while the machines installed precast concrete segments to form the permanent lining as they advanced.

Timeline

  1. 18 September 2024: Olga began its drive from St Jodok.

  2. 18 September 2025: The exploratory tunnel made the first underground Austria-Italy border connection.

  3. 28 July 2026: Both main railway bores were opened at the border.

  4. 25 August 2026: Wilma completed its western bore drive at Navis.

  5. 24 November 2026: Olga completed the eastern bore excavation at Navis.

Market Landscape

The Brenner Base Tunnel is a central piece of the Brenner corridor, the Alpine rail route linking Germany and Austria with Italy. Its revised timeline, with regular service now targeted for 2034 and the forecast cost at €11.7 billion, places this milestone within a project that is running behind its original plan.

For travelers, the tunnel is projected to cut the Innsbruck-Fortezza passenger journey from 80 minutes to 25 minutes once it is in service. Regular service is not expected until 2034, so the change will not affect rail trips for several years.

The takeaway

The eastern bore's completion shows the tunnel's main excavation is nearly done, but its budget and timeline have both moved. Readers planning long-distance Alpine rail travel should expect service to begin later than originally announced.

What happens next

Regular train services are targeted for 2034, with BBT SE expecting construction to finish in 2033 and testing and approvals scheduled for 2034.