Buss Terminal Eemshaven Starts Offshore Wind Marshalling
The Dutch port begins handling components for two North Sea wind projects totaling 1,695 megawatts.
Updated on Nov. 24, 2026 in Transportation

Buss Terminal Eemshaven has started marshalling operations for the Nordseecluster B and OranjeWind offshore wind developments. The terminal will handle storage, pre-assembly and load-out of monopile foundations and wind turbine generators.
Why it matters
The terminal's role as a logistics base supports the construction pipeline for two large offshore wind farms in the North Sea. Coordinating foundations and turbines in parallel at one site aims to streamline the sequencing of component deliveries.
The two projects total roughly 1,695 MW of offshore capacity, with 60 monopile foundations for Nordseecluster B and 53 turbine generators for OranjeWind passing through the terminal. Individual Nordseecluster B monopiles weigh up to 1,350 metric tons, and the source does not state the contract value.
The players
RWE
A German energy company and partner in both the Nordseecluster B and OranjeWind offshore wind projects, active in renewable generation across Europe.
TotalEnergies
A French multinational energy company and partner with RWE in the OranjeWind project in the Dutch sector of the North Sea.
Norges Bank Investment Management
The investment management arm of Norway's central bank, which co-develops the Nordseecluster B project with RWE.
Buss Terminal Eemshaven
A port terminal in Eemshaven, Netherlands, operated by Buss, that handles marshalling and load-out for offshore wind components.
The details
The terminal is handling marshalling, pre-assembly and load-out using Buss Blocks, the company's proprietary monopile support and storage system. A new heavy-duty quay supports turbine load-in and monopile load-out, with turbines and foundations handled in parallel on site.
Timeline
Operations for the two projects are underway as of late November 2026.
Over the next few months, the terminal will serve as the logistics base for storage, pre-assembly and load-out.
Delivery and installation vessels will sail in and out of the port over the coming year.
OranjeWind load-out is anticipated in spring 2027.
Roadmap
The Buss Blocks system is designed to give greater flexibility in component sequencing than conventional dune-based storage, and this deployment applies it to two concurrent North Sea projects. The approach reflects the broader move toward port-based staging of large offshore wind components as project sizes grow.
For readers following European energy supply, the terminal's work determines when the two wind farms can be assembled and connected to the grid. The source does not indicate any direct change to consumer electricity prices.
The takeaway
Large offshore wind projects depend on port terminals that can store, pre-assemble and load out heavy components in sequence. Watching these logistics hubs offers a useful gauge of whether project timelines are on track.
What happens next
Load-out of OranjeWind turbine generators is anticipated in spring 2027, and vessel traffic at the port is expected over the coming year.