RWE Receives First Monopiles for Nordseecluster B
The first 10 of 60 foundations for the 900MW Nordseecluster B offshore wind project were unloaded at Eemshaven, Netherlands.
Updated on Nov. 23, 2026 in Transportation

RWE received the first 10 monopile foundations for the 900MW Nordseecluster B offshore wind project at Eemshaven in the Netherlands. The foundations were unloaded at the Buss Ports heavy-lift terminal, and 60 monopiles will be handled at the terminal during 2026 and 2027.
Why it matters
The shipment marks a construction milestone for a project that is expected to add substantial renewable generation off Germany's coast. The Buss Terminal Eemshaven's storage areas and port infrastructure are central to moving foundations of this size into the build phase.
Each foundation measures approximately 81 metres in length and weighs approximately 1,350 tonnes, with 60 monopiles manufactured by Dajin Heavy Industry and handled at Eemshaven during 2026 and 2027. The stub does not report whether delivery pacing or project cost has changed.
The players
RWE
RWE is a German multinational energy company and a major developer of offshore wind farms in the North Sea.
Norges Bank Investment Management
Norges Bank Investment Management is the investment arm managing Norway's sovereign wealth fund and holds a 49% stake in Nordseecluster.
Dajin Heavy Industry
Dajin Heavy Industry is a Chinese manufacturer of wind tower and offshore wind foundation structures.
Amazon
Amazon is a multinational technology company that has signed renewable power purchase agreements to supply its data centres.
The details
The 60 monopiles were manufactured and supplied by Dajin Heavy Industry and unloaded at the Buss Ports heavy-lift terminal in Eemshaven. The Nordseecluster is being developed about 50 kilometres north of the German island of Juist, with the A phase at 660MW and RWE holding a 51% stake alongside Norges Bank Investment Management's 49%.
Timeline
Earlier in 2026: RWE signed a power purchase agreement with Amazon covering 110MW from Nordseecluster B.
2026: Monopile handling at the Eemshaven terminal begins.
Early 2027: Nordseecluster A is scheduled to become fully operational.
2027: Foundation installation for Nordseecluster B begins.
2028: Installation of 60 turbines is due.
Transportation Outlook
The Eemshaven delivery reflects a broader pattern in which Dutch and German North Sea ports are being used as heavy-lift staging hubs for large offshore wind foundations. The Nordseecluster B schedule places foundation installation in 2027 and turbine installation in 2028, extending a build-out that has relied on specialised port infrastructure.
For electricity customers, the project is expected to generate about 6.5TWh of renewable electricity annually once operational. Consumers in the region may see added renewable supply as the schedule advances through 2027 and 2028.
The takeaway
Large offshore wind projects depend on coordinated port logistics, with foundation deliveries timed years ahead of turbine installation. Tracking monopile arrivals offers an early indicator of whether construction stays on schedule.
What happens next
Foundation installation for Nordseecluster B is due to begin in 2027, with 60 turbines scheduled for installation in 2028 and commercial operations expected in early 2029.