Perseus Mining Nyanzaga Mine 88.4% Complete

Perseus Mining reports Tanzania's Nyanzaga gold project has reached 88.4% completion and forecasts a final cost of US$553 million to US$563 million.

Updated on Nov. 21, 2026 in Public Companies

Bold flat-color editorial illustration of two steel leaching tanks and a grinding mill on red earth beneath a cream sky, evoking a gold mining project nearing completion.
Perseus Mining said its Nyanzaga gold project in Tanzania was 88.4% complete at the end of September, with final costs now forecast at US$553 million to US$563 million. AI Illustration. Upload story photo >

Perseus Mining said its 80%-owned Nyanzaga gold project in Tanzania was 88.4% complete at the end of September 2026. The company forecasts the final project cost at US$553 million to US$563 million, above the US$523 million set at the April 2025 investment decision.

Why it matters

The cost increase is attributed to waste rock being mined faster than originally planned during pre-production. First gold is expected in January 2027, which would move the project toward commercial production.

Perseus has spent US$407.6 million of the US$483 million approved construction budget, while pre-stripping has reached 4.6 million bank cubic metres. The company held US$900 million in cash and bullion on 30 September 2026, but the forecast final cost still depends on completing the remaining work.

The players

Perseus Mining

Perseus Mining is an Australian-listed gold producer that owns 80% of the Nyanzaga project in Tanzania.

The details

Perseus said all three tailings storage facility embankments are complete and all 28 generators of the back-up power station are installed. Ring gears and motors are installed on both grinding mills, and the leaching tanks are complete, with first ore mined and stockpiled at 0.72 grams of gold per tonne.

Timeline

  1. 2024: Perseus acquired the Nyanzaga project.

  2. April 2025: Investment decision set the project cost at US$523 million.

  3. 27 October 2026: Perseus reported 88.4% completion.

  4. January 2027: First gold is expected.

  5. April to June 2027: Commercial production is planned.

Market Landscape

The Nyanzaga project's cost revision from US$523 million to a forecast US$553 million to US$563 million follows the April 2025 investment decision that set the original baseline. The company's progression toward first gold in January 2027 positions it to begin gold production from a Tanzanian project it acquired in 2024.

For investors holding Perseus Mining shares, the revised cost forecast and expected first gold in January 2027 are the key milestones to track. The company's US$900 million in cash and bullion on 30 September 2026 indicates its funding position as construction moves toward production.

The takeaway

Investors and observers should watch whether Perseus meets its first-gold timing and keeps final costs within the forecast range as the project moves into production.

What happens next

Perseus expects Nyanzaga to pour its first gold in January 2027, with commercial production planned for April to June 2027.