Perseus Mining Starts Feeding Ore to Nyanzaga Plant

The Tanzanian gold project is in commissioning as Perseus Mining targets a first gold pour in early 2027.

Updated on Nov. 19, 2026 in Public Companies

Wide photograph of a gold processing plant with a long conveyor carrying ore across red earth under a bright sky, with dry scrub on the horizon.
Perseus Mining has begun feeding ore into the plant at its 80%-owned Nyanzaga gold project in Tanzania, targeting a first gold pour in early 2027. AI Illustration. Upload story photo >

Perseus Mining has fed first ore into the plant at its Nyanzaga gold project in Tanzania and is ramping up commissioning. The company completed a revised ore reserve estimate of 4.0 million ounces of gold in February 2026.

Why it matters

The project's progress toward production adds a large gold resource to the market and advances a development that has been in the works for years. The revised reserve figure and planned output give investors and the broader mining sector a clearer view of the project's expected scale.

The February 2026 ore reserve of 90.9 million tonnes grading 1.38 g/t gold is up 73% over the April 2025 estimate. As of March 31, 2026, $220.3 million of the estimated $523 million capital expenditure had been incurred, with $124.9 million more committed.

The players

Perseus Mining

Perseus Mining is an Australian gold mining company that owns the Nyanzaga project in Tanzania.

Lycopodium

Lycopodium is an engineering firm serving as the engineering, procurement and construction management contractor for the Nyanzaga project.

The details

Perseus Mining owns an 80% contributing interest in the Nyanzaga project, with the Tanzanian government holding the remaining 20% as a noncontributing interest. The project, in the Lake Victoria Goldfields of north-west Tanzania, is being built as a large-scale open-pit operation with engineering and construction management by Lycopodium.

Timeline

  1. February 2026: Revised ore reserve estimate of 4.0 million ounces completed.

  2. March 31, 2026: Construction workforce exceeded 3,162 people, mostly local.

  3. Late November 2026: Commissioning of the 220 kV grid connection expected.

  4. Early 2027: First gold pour targeted.

  5. 2028 to 2041 financial years: Production expected to exceed 200,000 oz/y.

Market Landscape

The Nyanzaga project adds a major open-pit operation to the Lake Victoria Goldfields, a gold-producing belt in north-west Tanzania. Its 4.0 million ounce reserve and planned output above 200,000 oz/y from 2028 would place it among significant new gold supplies in the region.

For investors holding Perseus Mining shares, the project's progress toward production is the key milestone to watch as capital spending continues. Gold supply additions of this scale can affect commodity pricing and the broader market for gold-linked holdings.

The takeaway

Investors tracking Perseus Mining should watch for commissioning milestones and the first gold pour as the Nyanzaga project moves from construction into production. Progress against the $523 million capital budget and the 2027 start target will indicate execution on the project.

What happens next

Commissioning of the 220 kV grid connection is expected in late November 2026, and first gold pour is targeted for early 2027.

Further reading

Track more corporate developments in the Public Companies section.

Source note: This article includes information reported by Mining Weekly.