Offshore Oil Engineering Wins $800M QatarEnergy Contract
The 66-month project covers more than 100 km of subsea pipelines, power cables and umbilicals in Qatar's Maydan Mahzam redevelopment.
Updated on Nov. 21, 2026 in Oil and Gas

Offshore Oil Engineering Co has signed an contract worth about $800 million, or AED 2.94 billion, with QatarEnergy for subsea pipelines, power cables and umbilicals. The company disclosed the award in a stock exchange filing published on November 20.
Why it matters
The award gives Offshore Oil Engineering Co a large, multi-year role in a major Qatari offshore project tied to the Maydan Mahzam redevelopment. It also reflects continued investment in offshore infrastructure in Qatar's energy sector.
The contract is valued at about $800 million (AED 2.94 billion) and covers more than 100 km of pipelines, power cables and umbilicals scheduled over 66 months. The filing does not state how the monthly payments will be distributed beyond being based on construction progress.
The players
QatarEnergy
QatarEnergy is Qatar's state-owned energy company, responsible for the country's oil and gas production and major offshore development projects.
Offshore Oil Engineering Co
Offshore Oil Engineering Co is an engineering and construction contractor specializing in offshore oil and gas infrastructure projects.
PTSC Mechanical Construction
PTSC Mechanical Construction is a mechanical construction contractor that was separately awarded a Maydan Mahzam package by QatarEnergy.
The details
Under the EPIC2 package, Offshore Oil Engineering Co will manage the project and handle detailed engineering, procurement, construction, transport, installation and pre-commissioning, including associated facilities. QatarEnergy will pay monthly based on construction progress, and the contract is named EPIC2 MM Subsea Pipeline, Power Cables and Umbilicals.
Timeline
September: PTSC Mechanical Construction was awarded a Maydan Mahzam package by QatarEnergy.
October: Offshore Oil Engineering Co announced it had won the EPIC2 package of the Maydan Mahzam redevelopment.
November 20: Offshore Oil Engineering Co disclosed the $800 million contract in a stock exchange filing.
Season Trajectory
The EPIC2 award is one of several packages QatarEnergy has allocated under its Maydan Mahzam redevelopment, following the separate September award to PTSC Mechanical Construction. Together these contracts show the redevelopment moving from planning into execution across multiple contractors.
For consumers, the award has no immediate effect on prices or availability. The project's 66-month timeline means construction and pre-commissioning milestones will unfold over several years.
The takeaway
Large offshore energy projects are delivered through multi-year contracts split across several specialist contractors. Following award announcements and construction milestones gives a clearer picture of how such projects progress.