Azneft Acquires Four Drilling Rigs From China

Two of the four rigs have passed factory acceptance tests, with the rigs built by a subsidiary of China National Petroleum Corporation.

Updated on Nov. 20, 2026 in Oil and Gas

Offshore drilling derrick standing on a platform above calm, grey-green shallow water under a pale overcast sky.
Azerbaijan's state oil association Azneft has acquired four drilling rigs from China's BOMCO, with the first delivered in October for shallow-water operations. AI Illustration. Upload story photo >

SOCAR's Azneft Production Association has acquired four new drilling rigs from China, manufactured by BOMCO (Baoji Oilfield Machinery Co., Ltd.) to Azneft's order. Two of the rigs passed factory acceptance tests and were accepted, and the first rig was delivered to Azerbaijan in October 2026.

Why it matters

The rigs are intended for shallow-water drilling operations, and their arrival supports Azerbaijan's efforts to modernize equipment used in its oil production. Because the remaining rigs will be delivered in stages, operational capacity is expected to build over time rather than all at once.

Azneft has acquired four drilling rigs, two of which passed factory acceptance tests and were accepted. The remaining two rigs' delivery schedule and final acceptance status are not yet confirmed in the available reporting.

The players

SOCAR (State Oil Company of the Azerbaijan Republic)

SOCAR is Azerbaijan's state-owned oil and gas company, responsible for the country's upstream and downstream petroleum activities.

BOMCO (Baoji Oilfield Machinery Co., Ltd.)

BOMCO is a Chinese manufacturer of oilfield machinery and a subsidiary of China National Petroleum Corporation.

China National Petroleum Corporation (CNPC)

CNPC is one of China's largest state-owned oil and gas companies, with extensive international upstream and oilfield-services operations.

The details

The rigs were ordered from BOMCO, a subsidiary of China National Petroleum Corporation, under a contract signed on December 9, 2025. Following assembly and commissioning, the rigs will be transported to the shallow-water Gunashli field and installed before operations begin, where they will be used for sidetrack drilling and well workover operations.

Timeline

  1. December 9, 2025: Azneft and BOMCO signed the drilling rig contract.

  2. October 2026: The first rig was delivered to Azerbaijan.

  3. November 20, 2026: Azneft's acquisition of the four rigs was reported.

Industry Context

The purchase reflects a continuing pattern in which Azerbaijan's state oil operators source drilling equipment from Chinese manufacturers linked to CNPC, extending the Gunashli field's shallow-water capacity. The rigs represent an incremental fleet addition rather than a new development program.

Readers following oilfield services and equipment supply can track the remaining two rigs' staged deliveries as they arrive in Azerbaijan. The arrivals indicate when sidetrack and workover capacity at Gunashli will expand.

The takeaway

Equipment acquisitions like this one signal where operators are investing to maintain production from mature fields. Watching delivery and acceptance milestones offers a practical gauge of how quickly that investment reaches operations.