Trans Mountain Finishes Capacity Project Early
Drag-reducing additive lifts pipeline capacity about 10 per cent, two months ahead of schedule.
Updated on Nov. 27, 2026 in Oil and Gas

Trans Mountain Corp. completed a pipeline capacity project two months ahead of schedule by adding a drag-reducing chemical additive to the crude flowing through the line. The pipeline's capacity is now 980,000 barrels per day, and a further 210,000 barrels per day expansion is scheduled to enter service by the end of 2028.
Why it matters
The project lets the existing pipeline move more crude without new pipe, a faster route to added throughput than new construction. Higher volumes and revenue flow through to the company's financial results and to government payments tied to the line.
Third-quarter revenues rose to $825 million from $765 million a year earlier, and net income reached $132 million versus $127 million. Year to date, Trans Mountain has paid $1.45 billion to the federal government in interest payments, dividends and return of capital distributions, though the filing does not break out how much of that is tied to the capacity project.
The players
Trans Mountain Corp.
Trans Mountain Corp. operates the Trans Mountain pipeline system that carries crude oil from Alberta to British Columbia's coast.
The details
Capacity was raised by adding a drag-reducing chemical additive to the crude flowing through the pipeline, which increases throughput by about 10 per cent. A further expansion of 210,000 barrels per day, using new pipeline segments and pump stations, is expected to come into service by the end of 2028.
Timeline
During the third quarter of 2026, the pipeline shipped 840,000 barrels per day on average.
The capacity increase project was completed two months ahead of schedule.
So far in 2026, Trans Mountain has paid $1.45 billion to the federal government.
The further 210,000 barrels per day expansion is expected to enter service by the end of 2028.
Oil and Gas
Adding drag-reducing additives to existing crude lines is a way to raise throughput without waiting for new pipe to be built, and this project sets that approach against the larger 210,000 barrels per day expansion due by the end of 2028. It shows how operators can squeeze more volume from current infrastructure while longer-term expansions proceed.
For Alberta residents, the project affects the flow of crude through the province's export infrastructure and the payments the pipeline makes to government. The increase is an operational change to an existing line, so it does not by itself alter fuel prices or local service.
The takeaway
Operators can add meaningful throughput to existing pipelines through additives, which can deliver capacity sooner than new construction. Readers tracking Canadian energy infrastructure should watch whether the 2028 expansion stays on schedule.
What happens next
A further 210,000 barrels per day pipeline expansion is expected to come into service by the end of 2028.