Orange Proposes ReuNION Cable Extension to Singapore
Orange and consortium partners are seeking investors and partners to extend the ReuNION subsea cable from La Réunion to Southeast Asia.
Updated on Nov. 18, 2026 in Data Centers

Orange, La Réunion Connectée, and Reunicable et Telco Oi have announced a proposed extension of the ReuNION subsea cable to Singapore. The first phase linking La Réunion to South Africa is scheduled for provisional launch in early 2029.
Why it matters
The proposed extension would add a major fiber route across the Indian Ocean, expanding submarine connectivity between Réunion, Africa and Southeast Asia. The project shows how regional telecom operators are seeking outside investment to build new international capacity.
The Phase 1 section carries 16 fiber pairs at 20 Tbps each, for a total of 320 Tbps, with the Singapore extension planned at 24 fiber pairs. Investors for the extension have not been confirmed, and marine studies remain underway.
The players
Orange
Orange is a major French telecommunications operator involved in more than 40 submarine cables totaling nearly 450,000 km of fiber.
La Réunion Connectée
La Réunion Connectée is a consortium partner working on the ReuNION cable project connecting La Réunion to international networks.
Reunicable et Telco Oi
Reunicable et Telco Oi is a partner in the ReuNION project, which operates in the telecom sector serving La Réunion.
The details
The consortium is seeking co-investors for the extension, and the system's open-cable design would let them add branching units and choose landing points. Phase 1 is supported by European funding through the Connecting Europe Facility and the European Regional Development Fund.
Timeline
January 2025: Orange began shutting off its copper network on Réunion.
2027: The SAFE cable is scheduled for decommissioning, and cable deployment begins.
2028: Cable deployment is scheduled to continue.
Early 2029: Provisional launch of the first ReuNION phase is expected.
2030: Orange's copper network shutoff on Réunion is due to be completed.
The Tech Race
The ReuNION project would reduce Réunion's dependence on METISS, which will become the island's only international cable once SAFE is decommissioned in 2027. Extending the cable to Singapore positions the consortium to compete for Indian Ocean connectivity against established submarine routes.
For internet users on Réunion, the planned ReuNION cable would add significant international capacity once the older SAFE cable is retired in 2027. Businesses and households that depend on the island's connectivity could see more bandwidth as Orange shifts its copper network to fiber.
The takeaway
Undersea cable projects like ReuNION show how regional networks are being rebuilt with new fiber routes and outside investment. The timeline from proposal to launch stretches several years, so connectivity gains will arrive gradually.
What happens next
Marine studies are underway, with cable deployment scheduled for 2027 and 2028, and provisional launch of the first phase expected in early 2029.
Further reading
Explore more on Data Centers to see how undersea cables link the networks that power cloud services.
Source note: This article includes information reported by Datacenterdynamics.