A Government Accountability Office review found none of five agencies with new data centers fully met a federal energy and water assessment requirement.
Updated on Nov. 19, 2026 in Data Centers

Live Poll
Should your community pause new AI data centres until their resource impacts are studied?
The Government Accountability Office found that none of the five federal agencies building new data centers fully met a federal energy and water assessment rule issued by the Office of Management and Budget in January 2025. The review covered 24 agencies that reported a combined 1,392 data centers as of March 2026.
Why it matters
The findings show gaps in how federal agencies measure and plan the energy and water demands of their computing facilities, which can be significant given the scale of modern data centers. Because the underlying requirements expired on September 30, 2026, the GAO did not make formal recommendations to the agencies.
Of the 1,392 data centers reported by 21 federal agencies as of March 2026, seven are new facilities, and all five agencies operating them were rated as only partially addressing the energy and water assessment rule. The review does not establish whether any assessments will be completed on time for facilities still in planning.
The players
Government Accountability Office
The Government Accountability Office is the independent, nonpartisan audit and evaluation arm of the U.S. Congress, often called the investigative watchdog of federal spending.
Office of Management and Budget
The Office of Management and Budget is the White House agency that oversees the execution of the president's budget and issues government-wide management policy directives to federal agencies.
The details
Under the OMB memorandum, agencies building or substantially upgrading a facility were required to commission an assessment by certified data center energy efficiency specialists and to review its recommendations with their chief sustainability officer and facilities management staff. Agriculture and the Centers for Medicare & Medicaid Services provided no evidence the assessment was carried out during design, while the Nuclear Regulatory Commission did not show how it coordinates with its chief sustainability officer.
Timeline
January 2025: OMB issued memorandum M-25-03 requiring energy and water assessments.
December 2023: The Federal Data Center Enhancement Act passed as part of the National Defense Authorization Act.
March 2026: 21 agencies reported a combined 1,392 data centers.
September 30, 2026: The OMB energy and water requirements expired.
October 16, 2026: The Department of Commerce finalized a resource evaluation policy while the report was under review.
Roadmap
The review follows the Federal Data Center Enhancement Act passed in December 2023, which set the framework for federal data center consolidation and efficiency. The findings show that the energy and water assessment requirements implemented under that framework were only partially met before both the OMB rule and the underlying provisions sunset.
Because federal data centers draw power and water on a scale comparable to large towns, the agencies' assessment practices can influence the utility loads and local resources in the regions where these facilities are located. The findings signal that agencies may still need to document energy and water planning before building new facilities.
The takeaway
Federal agencies planning new data centers should document energy and water assessments during design rather than after construction begins. Watching whether agencies carry these practices into future facilities is a useful signal of how seriously energy use is being managed.
What happens next
Energy plans to obtain its required assessment once construction of its new data center begins in July 2027.
Further reading
For broader context on how these facilities are reshaping power demand, see the Data Centers section.
Source note: This article includes information reported by Smart Water Magazine.
Live Poll
Should your community pause new AI data centres until their resource impacts are studied?