Freemelt Wins Tungsten Order for ITER Fusion Work

Swedish manufacturer Freemelt will supply tungsten subassemblies to French firm Alsymex for early fusion qualification testing.

Updated on Nov. 16, 2026 in Nuclear

Isometric editorial illustration of dark tungsten blocks seated in rows on a copper plate, showing a modular assembly for fusion engineering work.
Swedish manufacturer Freemelt won a SEK 3.3 million order from French firm Alsymex to produce tungsten subassemblies for ITER fusion energy qualification testing. AI Illustration. Upload story photo >

Freemelt has received an order from Alsymex, a subsidiary of French technology group ALCEN, to manufacture tungsten subassemblies worth SEK 3.3 million ($326,000). The components support an early qualification campaign tied to the ITER fusion energy project.

Why it matters

ITER decided to replace beryllium with tungsten in plasma-facing applications, making tungsten components central to the project's engineering. The order shows fusion energy emerging as a commercial market for specialist manufacturers.

The SEK 3.3 million order is a fraction of the SEK 55 million Freemelt earlier received from Fusion for Energy for JT-60SA. Freemelt produces tungsten bricks joined to copper substrates using electron beam powder bed fusion, and the parts will go on to bonding and high heat flux testing.

The players

Freemelt

Freemelt is a Swedish manufacturer using electron beam powder bed fusion that has named fusion energy a strategic growth market.

Alsymex

Alsymex is a subsidiary of French technology group ALCEN that holds several contracts with Fusion for Energy.

The details

Freemelt will manufacture subassemblies of tungsten bricks joined to copper substrates for the Small Scale Mock-up program. The parts will proceed to bonding and high heat flux testing, and the company has named fusion energy a strategic growth market alongside medtech and defense.

Timeline

  1. Final delivery of the tungsten subassemblies to Alsymex is scheduled for the first quarter of 2027.

The Big Picture

ITER's decision to replace beryllium with tungsten in plasma-facing applications drives the qualification work this order supports. The subassemblies feed the Small Scale Mock-up program that tests those parts before wider use.

Tungsten components tested for fusion reactors could eventually influence the durability of future power plants. The timeline depends on qualification results, and the first delivery of parts is not due until the first quarter of 2027.

The takeaway

Commercial orders for fusion components are moving from research programs toward supply chains with defined delivery schedules. Watching qualification results will show whether tungsten parts meet the demands of future reactors.