Sanral Opens Kaaimans Pass Lanes for Festive Season
All lanes through Kaaimans Pass will be open in both directions from 15 December to 6 January, while N2 roadworks east of Wilderness continue.
Updated on Nov. 25, 2026 in Construction

Live Poll
Do you think road upgrades are worth the travel disruption they cause?
Sanral will open all lanes through Kaaimans Pass in both directions from 15 December to 6 January for the festive season. Roadworks east of Wilderness will continue to restrict traffic to one lane each way.
Why it matters
The N2 upgrade is intended to improve the route between Kraaibosch and Die Vleie in the Western Cape. Pointsmen will manage traffic at the Salinas, Hoekwil, Astron and Kleinkrantz intersections during the holiday period.
The N2 upgrade is split into an 8 km first phase and a 7 km second phase, with pointsmen staffed daily from 06:00 to 18:00 at four intersections. The source does not state the project's total cost or whether Phase 1 will finish on schedule.
The players
Sanral
The South African National Roads Agency Limited is the state-owned company responsible for managing and developing the country's national road network.
The details
Sanral has opened all lanes through Kaaimans Pass in both directions for the festive season, from 15 December to 6 January. One lane remains open in each direction between Wilderness and Die Vleie, and the pass remains hazardous because of the terrain.
Timeline
September 2023: Phase 1 of the N2 upgrade began.
February 2025: Construction on Phase 2 started.
15 December to 6 January: All lanes open through Kaaimans Pass.
Before the holiday season: Phase 1 construction is scheduled for completion.
End of 2028: Phase 2 is expected to be completed.
Construction Pipeline
The Wilderness works form part of Sanral's phased N2 upgrade, which began in September 2023 and continues with a second phase starting in February 2025. Phase 2 is expected to be completed towards the end of 2028.
Motorists travelling the N2 should expect single-lane restrictions between Wilderness and Die Vleie during the holiday period. Allow extra time at the Salinas, Hoekwil, Astron and Kleinkrantz intersections, where pointsmen are on duty from 06:00 to 18:00.
The takeaway
Motorists heading to the Garden Route should plan for single-lane sections near Wilderness and allow extra travel time through the festive period.
What happens next
Phase 2 roadworks between Touw River and Die Vleie are scheduled to continue until the end of 2028, with the first phase due for completion before the holiday season.
Further reading
Explore more Construction news for the Western Cape.
Source note: This article includes information reported by George Herald.