The state roads agency has appointed an independent consultant to audit payments on its Cradock to Hofmeyr road project.

Updated on Nov. 16, 2026 in Employment

Wide view of a partly finished road embankment cutting across dry Eastern Cape scrubland under clear sky, illustrating the Cradock to Hofmeyr road project.
SANRAL has appointed an independent consultant to audit payment complaints from subcontractors on its Cradock to Hofmeyr road project in the Eastern Cape. AI Illustration. Upload story photo >

Live Poll

Do you trust large companies to pay their subcontractors on time?

The South African National Roads Agency SOC Limited (SANRAL) received complaints from subcontractors on its Cradock to Hofmeyr road construction project about payment issues. The agency appointed an independent consultant to audit the contract after the complaints surfaced in early October 2026.

Why it matters

SANRAL only holds contractual agreements with main contractors, so subcontractors depend on those firms to pay them on time. The outcome of the audit could determine how the agency enforces payment terms on its projects in the Eastern Cape.

The contract sets a 14-day payment deadline for the main contractor to pay SMMEs after service is provided. The preliminary audit of payment records found no late payments to date, but allegations of unfair deductions, unfair treatment and lack of training remain unaddressed.

The players

South African National Roads Agency SOC Limited (SANRAL)

SANRAL is the state-owned entity responsible for South Africa's national road network, including the construction and maintenance of major roads.

The details

SANRAL received complaints from subcontractors working on the Cradock to Hofmeyr road construction project about payment issues by the main contractor. The agency appointed an independent consultant to perform an in-depth audit of the contract, and the initial outcomes of that audit have now been received.

Timeline

  1. Early October 2026: Subcontractor complaints surfaced and the audit process began.

  2. 11 November 2026: SANRAL received subcontractor complaints in Gqeberha.

  3. November 2026: The final audit report is expected.

Economic Context

The dispute tests whether the 14-day payment clause in SANRAL's contracts protects small subcontracting businesses on public road projects. The preliminary finding of no late payments places the complaints about deductions and treatment at the centre of the final audit.

Small businesses subcontracting on SANRAL projects are protected by a 14-day payment deadline that the main contractor must meet. Subcontractors who face unfair deductions or treatment can raise those concerns with the agency as the audit proceeds.

The takeaway

Payment terms in public infrastructure contracts only protect subcontractors when they are audited and enforced. Watch whether the final November report addresses the deductions and treatment complaints left open by the preliminary review.

What happens next

SANRAL is expected to receive the final audit report in November 2026, after which it will decide how to act on the findings.