South Africa Expands AI Data Centre Capacity

South Africa has more than 60 operational data centres, and a project pipeline could more than double capacity, prompting a human rights review.

Updated on Nov. 24, 2026 in Tech

South Africa Expands AI Data Centre Capacity

Live Poll

Do you support new data centres being built in your community?

South Africa is expanding AI data centre capacity, with more than 60 operational facilities and a pipeline that could more than double capacity. The South African Human Rights Commission called for public submissions in May 2026 on the human rights implications of the expansion.

Why it matters

Hyperscale facilities from operators including Teraco, Equinix and Microsoft are expanding amid cloud adoption and the global AI computing race. Questions over water use and land use for supporting solar farms are shaping the debate over who benefits from the build-out.

Operator-reported water-use figures put Teraco near 0.03 litres per kilowatt-hour, far below the tens of millions of litres per megawatt a year that traditional evaporative cooling can consume. Whether such efficiency holds across the wider pipeline has not been independently verified.

The players

South African Human Rights Commission

The national body established under the South African Constitution to promote and protect human rights, which called for public submissions on data centre expansion.

Teraco

A South African data centre operator that reported water-use efficiency figures near 0.03 litres per kilowatt-hour for its facilities.

Equinix

A global data centre and interconnection company that operates a facility outside Johannesburg.

Microsoft

A US technology company whose cloud and AI infrastructure investment is among the drivers of hyperscale expansion in South Africa.

The details

Equinix's data centre outside Johannesburg employed around 750 people during construction and now has 26 permanent staff. A proposed eThekwini campus of approximately 400 MW, valued at $3 billion to $10 billion, is estimated to create 500 permanent roles and 5,000 construction jobs, and the eThekwini Municipality has signed a preliminary Memorandum of Agreement with the developer.

Timeline

  1. May 2026: The South African Human Rights Commission called for public submissions on the human rights implications of data centre expansion.

  2. 20 November 2026: Deputy Minister Gina spoke at the 2026 CSIR Excellence Awards on the sector.

Big Picture

The Presidency projects R1-1.4 trillion in investment and hundreds of thousands of broader digital jobs by the end of the decade. PricewaterhouseCoopers estimates a conservative 1.2% cumulative GDP increase over a decade under realistic inequality scenarios.

For South Africans, the expansion may bring construction work and some permanent roles, though the reported permanent headcount at existing facilities is small. Residents in water-stressed regions may see the water-use trade-offs of cooling technology play out in local planning decisions.

The takeaway

Headline capacity and investment figures can obscure how few permanent jobs a large facility creates, so the gap between projected and realised employment is worth tracking. Water-use claims are most useful when compared against the cooling method actually deployed.

Further reading

Explore more on data centers to see how hyperscale expansion is reshaping national infrastructure.

Source note: This article includes information reported by African News Agency.

Live Poll

Do you support new data centres being built in your community?