Utility Builds Power Lines for Microsoft Data Centers

Cheyenne Light, Fuel and Power Co. has agreed to build infrastructure serving three planned Microsoft data centers in Wyoming.

Updated on Nov. 25, 2026 in Data Centers

Utility Builds Power Lines for Microsoft Data Centers

Live Poll

Do you expect your electricity bills to rise because of new data centers in your area?

Cheyenne Light, Fuel and Power Co. entered agreements to build distribution and transmission infrastructure for three planned Microsoft data centers in Wyoming, with Microsoft paying for the work through contribution in aid of construction payments. The utility filed the redacted agreements with the Federal Energy Regulatory Commission.

Why it matters

The filing shows how a regional utility is absorbing a large wave of data center demand, with significant implications for the cost of building grid capacity. Cheyenne Light's parent, Bright Horizon Energy Corp., is positioning the utility around this growth.

Cheyenne Light has about 46,000 retail electric customers and set a peak load record of 439 MW in July, while its pipeline includes a 3-GW data center portfolio. The redacted Microsoft agreements do not disclose full contract terms, and the Wyoming Public Service Commission has yet to rule on the transmission tariff.

The players

Cheyenne Light, Fuel and Power Co.

A Cheyenne-based electric utility serving about 46,000 retail customers and a subsidiary of Bright Horizon Energy Corp.

Microsoft

A global technology company that is planning three data centers in Wyoming served by the utility's new infrastructure.

Bright Horizon Energy Corp.

A utility holding company formed by the merger of Black Hills Corp. and NorthWestern Energy Group, which owns Cheyenne Light.

The details

Under the agreements, Microsoft pays for the infrastructure through contribution in aid of construction payments. Cheyenne Light plans to serve the data centers through its Large Power Contract Service tariff and a proposed Large Customer Transmission Cost Adjustment Mechanism, and filed with FERC out of an abundance of caution given the agency's recent statements on transmission cost recovery for large load customers.

Timeline

  1. July: Cheyenne Light set a peak load record of 439 MW.

  2. September: The utility agreed to supply a Google data center in Cheyenne with 590 MW.

  3. Nov. 13: The merger creating Bright Horizon Energy Corp. took effect.

  4. 2027 to 2029: Planned construction of a 564-MW gas-fired power plant.

Roadmap

The filing responds directly to recent FERC statements on who should pay for transmission costs caused by large load customers such as data centers. It shows regional utilities moving to assign those costs to the developers creating the demand, a question now being tested across the grid.

How transmission costs are allocated will determine whether residential customers in the Cheyenne area bear part of the expense of new grid capacity for data centers. The proposed cost pass-through mechanisms are meant to shield customers from costs tied to the planned facilities.

The takeaway

Cost allocation for data center grid upgrades is becoming a central regulatory question, and how Wyoming regulators resolve the transmission tariff will set a precedent for similar utilities.

What happens next

The Wyoming Public Service Commission is expected to decide on the proposed transmission tariff by mid-2027.

Further reading

For more on the buildout, see Data Centers coverage across the Cheyenne region.

Source note: This article includes information reported by Utility Dive.