Data Center Rezoning Hearing Set for December 8

Western Power Development LLC seeks to rezone 1,275 acres near Casper for a data center and power generation project.

Updated on Nov. 25, 2026 in Data Centers

Data Center Rezoning Hearing Set for December 8

Live Poll

Would you support a large data center project in your county?

Western Power Development LLC is seeking to rezone 1,275 acres of Falls Ranch land near Casper for data center halls and on-site power generation. A public hearing before the Natrona County Planning and Zoning Commission is scheduled for December 8.

Why it matters

The request would convert vacant ranching, agriculture and mining land into an industrial park under a Planned Unit Development overlay, a step that follows Prometheus Hyperscale abandoning its own planned Falls Ranch data center project. Residents and local officials in Casper and Natrona County will weigh the zoning change at the hearing.

The proposal covers 1,275 acres, larger than the 940-acre site Prometheus Hyperscale originally planned, which was tied to a 1.5-gigawatt capacity and a $500 million valuation. The filing does not yet specify the planned computing capacity or power output for the new site.

The players

Western Power Development LLC

The company seeking the rezoning of the Falls Ranch land for a data center and on-site power generation project.

Prometheus Hyperscale

A data center developer that abandoned its planned Falls Ranch project and has since moved its campus to Uinta County.

Russell Gordy

A Texas oilman who owns SG Interests and Falls Ranch, the land at the center of the rezoning request.

The details

Western Power Development LLC, whose initial Wyoming filing was submitted November 2, is pursuing the change through a legal notice and public hearing process. The company seeks to establish the Falls Ranch Industrial Park through a Planned Unit Development overlay district on land currently zoned for ranching, agriculture and mining. Falls Ranch representatives said the shift to the new location will expedite and elevate the project for Natrona County.

Timeline

  1. September 1: Prometheus officials pitched industrial park zoning to county commissioners.

  2. October 28: Prometheus announced it was walking away from the project.

  3. November 2: Western Power Development LLC submitted its initial filing.

  4. November 25: Legal notice published announcing the upcoming public hearing.

  5. November 27: Deadline for written public comments; public hearing set for December 8 at 5:30 p.m.

Market Landscape

This rezoning effort picks up where Prometheus Hyperscale left off, moving the Falls Ranch data center plan into a new county review after the earlier 1.5-gigawatt project was dropped. It reflects how developers are seeking large power-intensive sites in Wyoming as competition for data center land intensifies.

Casper and Natrona County residents can submit written comments to the Natrona County Development Department through November 27. The outcome could shape nearby land use, traffic and utility demands for years to come.

The takeaway

Residents who want to affect the outcome can submit written comments before November 27 or attend the December 8 hearing. Watching how the commission handles the Falls Ranch request may signal how Wyoming counties approach large data center proposals.

What happens next

The Natrona County Planning and Zoning Commission will hold a public hearing on the rezoning request on December 8 at 5:30 p.m.

Further reading

Explore more coverage in the Data Centers section for context on projects like this one.

Source note: This article includes information reported by Oil City News.