Wyoming Supreme Court Upholds Pronghorn H2 Wind Lease
The unanimous ruling reverses a district court decision that had struck down the state land agreement for a Converse County wind project.
Updated on Nov. 27, 2026 in Politics

Live Poll
Should Wyoming lease public land for large wind projects in your community?
The Wyoming Supreme Court ruled unanimously on November 3, 2026, upholding the State Board of Land Commissioners' lease for the Pronghorn H2 wind energy project. The decision reverses a December 2025 district court ruling that had invalidated the lease.
Why it matters
The court found the land board followed its rules, and that wind leasing rules do not bar a project from supplying a hydrogen production facility. The ruling resolves a dispute over whether state land may be leased for such a purpose in Wyoming.
The Supreme Court ruling was unanimous, and the project spans about 46,000 acres, including 13,838 acres of state land. The Industrial Siting Council must still approve the project, and the timeline for that approval has not been set.
The players
Wyoming Supreme Court
The state's highest court, which issues final rulings on Wyoming law and whose decisions set binding precedent for state agencies and lower courts.
State Board of Land Commissioners
A five-member body of elected Wyoming officials that manages state trust lands and approved the Pronghorn H2 lease.
Governor Mark Gordon
Wyoming's governor, who supported the lease approval and serves as a member of the State Board of Land Commissioners.
Secretary of State Chuck Gray
Wyoming's secretary of state, who opposed the lease approval on the land board.
The details
The State Board of Land Commissioners approved the Pronghorn H2 lease in April 2025, with Governor Mark Gordon, Auditor Kristi Racines, Superintendent Megan Degenfelder and Treasurer Curt Meier supporting it while Secretary of State Chuck Gray opposed it. The district court had found the lease did not meet requirements because the project was primarily intended to supply a hydrogen plant rather than the transmission grid, a finding the Supreme Court reversed.
Timeline
April 2025: State Board of Land Commissioners approves the Pronghorn H2 lease.
December 2025: A district court judge strikes down the lease.
November 3, 2026: Wyoming Supreme Court upholds the lease.
Legal Context
The ruling clarifies how Wyoming's wind energy leasing rules apply to state trust land when a project serves an industrial end use rather than the transmission grid. It sets a precedent for how the state land board may approve future leases tied to hydrogen production.
The ruling clears a legal obstacle for the Pronghorn H2 project, but construction still depends on the Industrial Siting Council's approval, which could take several years. Residents near the project area may see changes to land use and nearby development over that period.
The takeaway
Land-use disputes over state trust lands can hinge on how a project's purpose is classified under agency rules. Readers following energy siting in Wyoming should watch the Industrial Siting Council process that comes next.
What happens next
The Industrial Siting Council must review the Pronghorn H2 project, and plaintiffs may request a rehearing within 15 days of the November 3, 2026 ruling.
Further reading
Explore more Wyoming legal news on state court rulings and land-use disputes.