Epsilon Energy Brings Parkman Development Online Early
The Powder River Basin project came online a month ahead of plan, and the company accelerated its next drilling program by two months.
Updated on Nov. 25, 2026 in Oil and Gas

Epsilon Energy announced on its third quarter 2026 earnings call on November 24, 2026, that its first operated Parkman development was brought online a month ahead of schedule. The company also accelerated its next three-well Parkman drilling program by two months.
Why it matters
Bringing wells online early and pulling drilling forward can speed production and cash flow from Wyoming acreage held by the company. Trading working interests and joint ventures also shift project costs to larger partners, which bears on how the company funds its development.
Epsilon's 3-well Bridle Bit pad in Campbell County posted a 30-day initial production roughly 30% above expectations, and the company pulled approximately 6 net locations forward through land transactions. The company did not disclose production volumes or cost figures tied to the early start.
The players
Epsilon Energy
Epsilon Energy is an independent natural gas and oil company with operations in the Powder River Basin and other U.S. basins.
The details
Epsilon traded working interests and entered joint ventures to unlock long-dated acreage in the Powder River Basin, with partners carrying project costs. Field crews also replaced 22 natural gas compressors and downgraded electrical service at 39 locations, a program the company said cut gross operating costs by $110,000 per month.
Timeline
Late September 2026: Bridle Bit Parkman wells placed on production, about a month ahead of plan.
November 24, 2026: Epsilon announced the Parkman development was online on its third quarter earnings call.
November 2026: One final compressor unit remains to be replaced this month.
2027: The company expects growth in production, cash flow and shareholder value, with new Permian and Marcellus wells planned.
Market Landscape
Epsilon's moves to trade working interests and enter joint ventures in the Powder River Basin reflect a broader pattern of independent producers sharing capital costs with larger operators to develop acreage faster. Accelerating Parkman drilling while lowering fixed costs puts the company on a path to compete more efficiently for basin capital.
For Wyoming residents, the early Parkman start and accelerated drilling could bring more activity and jobs to the Powder River Basin in the near term. The company's lower fixed cost base is designed to protect cash margins when commodity prices fall.
The takeaway
Lower operating costs and shared project funding can help an independent producer keep cash flowing through commodity price swings. Readers following Wyoming energy should watch whether the 2027 wells sustain that cost advantage as output ramps.
What happens next
Epsilon's next three-well Parkman drilling program is scheduled to begin two months earlier than planned, and the company has set its 2027 Permian and Marcellus well program for the coming year.