Groathouse Gathers Bids for Shooting Complex Events Center
Subcontractor bids are being collected for the roughly $10 million main events center at the Wyoming State Shooting Complex.
Updated on Nov. 17, 2026 in Industry

Groathouse Construction, the construction manager at risk, is collecting subcontractor bids for the main events center at the Wyoming State Shooting Complex. The building's estimated cost is roughly $10 million.
Why it matters
The project is moving forward with cost-saving layout and power decisions that affect how the complex is built across Wyoming. Locking in subcontracts early aims to get ahead of an expected steel price increase.
The board's approved changes save more than $150,000 by moving trap and skeet courses and roughly $500,000 by using single phase power with later conversion. The events center is estimated at roughly $10 million, but the final guaranteed maximum price is still pending.
The players
Groathouse Construction
Groathouse Construction is the construction manager at risk for the main events center at the Wyoming State Shooting Complex.
Wyoming State Shooting Complex
The Wyoming State Shooting Complex is a state-run facility whose main events center and sporting clays courses are under construction.
The details
Groathouse is collecting subcontractor bids in the weeks following the start of bid acceptance, with steel prices being locked in before January 1. The joint powers board agreed to shift trap and skeet courses from true north to northeast, because the true north layout would require moving more dirt, and to use single phase power with conversion to three phase for machinery.
Timeline
November 2026: The joint powers board discussed the cost changes at its meeting.
December 2026: The guaranteed maximum price is scheduled to be presented to the board.
Before January 1, 2027: Subcontracts are targeted for execution ahead of an expected steel price jump.
Fall 2027: The events center building is planned to be completed.
Construction Pipeline
The project's early steel procurement responds directly to the expected year-end jump in steel prices that is shaping bid timing across this bid cycle. Locking subcontracts before January 1 places the events center on a cost path set before that increase takes effect.
Cost-saving choices on layout and power could keep the complex's total construction budget closer to the planned figure. Visitors planning events at the complex may see the facility's limited full power RV spaces and its three large sporting clays courses shape scheduling.
The takeaway
Large public construction projects often lock in material and labor costs early, because the expected price changes ahead can outweigh the savings from waiting. Watching the December board presentation will show whether these early decisions hold.
What happens next
The guaranteed maximum price will be presented to the joint powers board at its December 2026 meeting, and subcontract execution is targeted before January 1, 2027.
Further reading
Explore more Construction coverage for related project updates across the state.
Source note: This article includes information reported by Powell Tribune.