Ur-Energy Estimates $35M Wastewater Plant Cost

Ur-Energy says a permanent wastewater treatment facility at its Lost Creek operation could cost up to $35 million.

Updated on Nov. 11, 2026 in Utilities

Bold vector editorial illustration of plain cylindrical filter vessels and a pipe manifold on a flat sagebrush plain under open sky.
Ur-Energy estimated on Tuesday that a permanent wastewater treatment facility at its Lost Creek operation in Wyoming could cost $33 million to $35 million, with $7.7 million spent through September 30. AI Illustration. Upload story photo >

Ur-Energy has estimated the capital cost of a permanent wastewater treatment facility at its Lost Creek operation at $33 million to $35 million, including a sand filtration system. The company had spent $7.7 million on the project through September 30.

Why it matters

Wastewater capacity has limited use of the sand filtration system, which removes fine particles from the wellfield and is designed to increase flow rates. The facility's timing is tied to regulatory approval for Mine Unit 5 production.

Ur-Energy's estimate of $33 million to $35 million compares with $7.7 million spent through September 30, with about $23 million projected for 2026 and $11 million for 2027. Whether the spending schedule holds depends on the pending regulatory review, which the source does not resolve.

The players

Ur-Energy

Ur-Energy is a uranium mining company that operates the Lost Creek in-situ recovery facility in Wyoming.

Wyoming Department of Environmental Quality

The Wyoming Department of Environmental Quality is the state agency that regulates environmental permitting and compliance, including the review of mining regulatory packages.

The details

Ur-Energy submitted the first phase of its Mine Unit 5 regulatory package to the Wyoming Department of Environmental Quality in September. The company expects the wastewater facility to begin operating in the first half of 2027, with regulatory approval in time to start Mine Unit 5 production in the first quarter of 2027.

Timeline

  1. September: Ur-Energy submits first phase of its Mine Unit 5 regulatory package.

  2. September 30: Cumulative wastewater facility spending reaches $7.7 million.

  3. 2026: Ur-Energy projects about $23 million in wastewater facility spending.

  4. First half of 2027: Wastewater facility expected to begin operating.

  5. First quarter of 2027: Expected start of Mine Unit 5 production.

Roadmap

The Lost Creek project's wastewater expansion follows the Wyoming Department of Environmental Quality's permitting path for in-situ uranium recovery mine units. Its progress will show whether the state's review timelines match the operator's expansion schedule.

For Wyoming residents, the project's wastewater facility and mine unit timeline affect regional water management and local employment tied to uranium operations. The schedule depends on regulatory approval that remains pending.

The takeaway

Large infrastructure costs can shape the timing of mining expansions, so readers should watch whether the Wyoming Department of Environmental Quality approves the Mine Unit 5 package on schedule. Regulatory milestones will determine when the wastewater spending begins to pay off in production.

What happens next

Ur-Energy expects regulatory approval in time to begin Mine Unit 5 production in the first quarter of 2027, and the wastewater facility is expected to begin operating in the first half of 2027.

Further reading

Explore more Wyoming utilities coverage for context on regional water and waste infrastructure.

Source note: This article includes information reported by TokenPost.