Morgantown Airport Hires Brian Belcher as Director

The city named Belcher its next airport director in August 2026, months after cutting ties with the prior director overseeing a runway extension.

Updated on Nov. 13, 2026 in Air Travel

Long concrete runway extension running toward a flat horizon under overcast daylight, with an idle yellow excavator parked at the edge of bare gravel shoulders.
Morgantown Municipal Airport hired Brian Belcher as airport director in August 2026, months after cutting ties with Jon Vrabel, who oversaw a runway extension needed for additional airline service. AI Illustration. Upload story photo >

Live Poll

Do you think your local airport is getting better or worse for travelers?

Morgantown Municipal Airport has hired Brian Belcher as airport director, announced in August 2026. The city had abruptly cut ties with Jon Vrabel, who oversaw the runway extension project, six months before Belcher's hiring.

Why it matters

The runway extension is required for other airlines to serve Morgantown Municipal Airport, and completing it is expected to unlock the airport's future potential. Passenger traffic more than doubled in 2025, with 15,300 enplanements compared with 7,700 in 2024.

Morgantown Municipal Airport surpassed 15,300 enplanements in 2025, nearly double the 7,700 recorded in 2024. The runway extension, 1,001 feet long, is now projected at about $70 million, up from an original $50 million estimate, with the city still awaiting a decision on $25 million in federal funding.

The players

Brian Belcher

Belcher previously worked in West Virginia and was named Morgantown Municipal Airport's director in August 2026.

Shelley Moore Capito

Capito is a United States Senator from West Virginia whose office urged the city to request congressionally directed funding for the runway project.

The details

The FAA cleared the city to proceed with the runway extension in November 2019, and construction began in March 2021. In June 2026, Morgantown City Council approved a $5,833,450 contract with Mountaineer Infrastructure for Phase 5A of the project, which was originally expected to take five years but is now on pace to take closer to a decade.

Timeline

  1. November 2019: FAA cleared the runway extension project to proceed.

  2. March 2021: Runway extension construction began.

  3. June 2026: City Council approved the $5.8 million Phase 5A contract.

  4. August 2026: Brian Belcher was announced as the next airport director.

  5. October 2026: The airport had reached about 12,400 enplanements in 2026.

Travel Outlook

The Morgantown runway extension, cleared by the FAA in November 2019, has stretched from an original five-year, $50 million plan toward a decade-long, roughly $70 million build. Leadership changes at the airport now sit inside that longer timeline, as passenger growth raises pressure to complete the runway needed for additional airline service.

Travelers using Morgantown Municipal Airport should expect the runway extension to continue for years, which will limit which airlines can serve the airport in the near term. Anyone planning flights from Morgantown should check current schedules directly with carriers, since service options depend on when the runway is completed.

The takeaway

Regional airports often depend on a single major infrastructure project to attract new airlines, and Morgantown's runway extension shows how long such work can take. Its timeline has roughly doubled from the original estimate, making steady project leadership important for the airport's growth.

Further reading

Explore more on Air Travel coverage for context on how regional airports are expanding service.

Source note: This article includes information reported by The Dominion Post.

Live Poll

Do you think your local airport is getting better or worse for travelers?