West Virginia Parkways Authority Began Interior Demolition
The authority has started work on its future Charleston headquarters after purchasing a former lodge building.
Updated on Oct. 4, 2026 in Construction

Live Poll
Do you support consolidating government operations into single facilities to improve service efficiency in your area?
The West Virginia Parkways Authority has initiated interior demolition at its future headquarters site. This move aims to consolidate fragmented customer service operations into a single location.
Why it matters
Current operations are spread across four separate facilities, creating accessibility and wayfinding challenges for the public. Consolidating into one building will centralize services for the 88-mile toll road.
The authority purchased the former Moose Lodge building for $700,000. The total project budget for the renovation is estimated between $8 million and $10 million.
The players
West Virginia Parkways Authority
This state entity manages the 88-mile West Virginia Turnpike toll road and provides associated customer service operations.
ZMM Architects and Engineers
This professional services firm was contracted to design the renovation and provide architectural oversight for the new headquarters.
The details
Contractors are currently removing non-structural drywall, plumbing, and electrical systems to prepare the site. This project will eventually replace the authority's existing headquarters on Piedmont Road and consolidate offices currently split between Charleston and Beckley.
Timeline
December 2025: The authority purchased the former Moose Lodge building.
May 2026: ZMM Architects and Engineers were contracted for the project.
September 2026: The board approved the start of interior demolition.
Early spring 2027: Construction drawings and design packages are expected to be finished.
Q1 2028: The authority expects to move operations into the new building.
Market Landscape
This project follows a pattern set by the consolidation of the West Virginia Parkways Authority operations to improve organizational efficiency. It marks a shift toward centralizing services that were previously fragmented across multiple regional sites.
The relocation aims to simplify customer service interactions by bringing disparate departments under one roof. Once completed, residents and commuters will no longer need to navigate multiple sites between Charleston and Beckley to access authority services.
The takeaway
Centralizing administrative offices can significantly reduce the complexity of public-facing operations. Organizations should prioritize accessibility when planning facility expansions to ensure consistent service delivery.
What happens next
Construction drawings and design packages are scheduled for completion by early spring 2027, followed by the expected relocation to the new facility in the first quarter of 2028.
Further reading
Find more updates on regional developments in the Construction section.
Source note: This article includes information reported by WV MetroNews.