Kenosha Reopens 22nd Avenue Stretch

The 50th Street to Washington Road segment reopened after completion of the city's eighth reconstruction segment on the north side.

Updated on Nov. 21, 2026 in Construction

Kenosha Reopens 22nd Avenue Stretch

Kenosha has reopened 22nd Avenue from 50th Street to Washington Road on the city's north side. Stark Pavement Corporation of Burlington completed the segment on time and within budget.

Why it matters

The reopening advances the city's multiyear reconstruction of 22nd Avenue, which began in 2018 and spans Birch Road to 89th Street. Completing segments on schedule and on budget keeps the remaining work on track for Kenosha residents who rely on the corridor.

The reopened segment is the eighth of nine planned phases in a reconstruction project that started in 2018. The source does not report the project's cost or the exact amount by which the segment came in under budget.

The players

Stark Pavement Corporation

Stark Pavement Corporation is a paving and road construction contractor based in Burlington that completed the segment.

The details

The segment, which ran from 50th Street to Washington Road, included utility relocation and roadway reconstruction with new concrete pavement. Stark Pavement Corporation of Burlington performed the reconstruction work and completed it on time and within budget.

Timeline

  1. 2018: Reconstruction of 22nd Avenue began with Segment 1.

  2. November 20, 2026: The 50th Street to Washington Road stretch reopened.

  3. 2030: Segment 9, from 18th Street to 15th Place, is scheduled.

Season Trajectory

The reopening continues the phased rebuilding of 22nd Avenue that started in 2018 with Segment 1, now nearing completion with only the ninth segment remaining. Scheduling the final segment for 2030 places the corridor's full reconstruction more than a decade after the first phase began.

Drivers using 22nd Avenue between 50th Street and Washington Road can again travel the reconstructed roadway with new concrete pavement. Commuters on the corridor should expect continued work on the remaining segments until the final one is finished.

The takeaway

Kenosha's phased approach to 22nd Avenue shows how a long corridor can be rebuilt segment by segment while keeping most of it open. Residents planning travel on the north side should check the city's schedule as the remaining segments proceed toward 2030.

What happens next

Segment 9, from 18th Street to 15th Place, is scheduled for 2030 to complete the 22nd Avenue reconstruction.