WSDOT Releases Final Bridge Replacement RFP

The Interstate Bridge Replacement's final request-for-proposals opens the design-build contract to Columbia River Constructors.

Updated on Nov. 24, 2026 in Business

WSDOT Releases Final Bridge Replacement RFP

Live Poll

Do you trust state officials to keep the Columbia River bridge project within budget?

The Washington State Department of Transportation released the final request-for-proposals and Schedule B progressive design-build contract documents on Nov. 23. Columbia River Constructors, a joint venture of Kiewit, Guy F. Atkinson and Traylor Bros., advanced as the sole remaining team after submitting a single qualification statement.

Why it matters

The project is a five-mile corridor linking Vancouver and Portland, and the contract's progressive approach lets costs be negotiated as designs evolve rather than fixed up front. Amtrak's decision to drop a $900 million Bridgeport rail yard in favor of redeveloping its 14th Street yard also shapes how the broader corridor works.

The estimated corridor cost runs from $13.5 billion to $15.2 billion, with the bridge contract valued at $3.3 billion to $3.885 billion. The first funded construction phase holds about $5.69 billion, while proposal prices remain unknown until bids are submitted.

The players

Columbia River Constructors

A joint venture of Kiewit, Guy F. Atkinson and Traylor Bros. that submitted the sole qualification statement for the bridge contract.

Washington State Department of Transportation (WSDOT)

The state agency overseeing the primary contract and the final request-for-proposals for the bridge replacement.

Oregon Department of Transportation

The Oregon agency co-overseeing the primary contract for the Interstate Bridge Replacement corridor.

Amtrak

The national passenger rail operator that scrapped its $900 million Bridgeport rail yard plan and will redevelop its 14th Street yard instead.

The details

WSDOT's final RFP covers two new fixed-span bridges west of the existing Interstate 5 bridges, and the qualification round closed in September. Open-book pricing and an independent cost-estimation process will be used to determine whether proposed costs are reasonable.

Timeline

  1. September 2026: Qualification round ended.

  2. Nov. 12, 2026: WSDOT advanced Columbia River Constructors as the sole remaining team.

  3. Nov. 23, 2026: WSDOT released the final request-for-proposals.

  4. March 24, 2027: Proposals are due.

  5. April 12-16, 2027: Interviews with proposers are scheduled.

Big Picture

The bridge replacement depends on roughly $1 billion still sought through the FTA's Capital Investment Grant program, a funding source that remains unsecured as the final RFP advances. This places the project's timeline and financing in dependence on federal grant approval before construction can be fully underwritten.

Commuters crossing between Vancouver and Portland will eventually face construction on the Interstate 5 corridor, with completion targeted for the fourth quarter of 2036. Local drivers should expect the bridge work to shape traffic patterns long before the new spans open.

The takeaway

Major infrastructure projects are often delivered through progressive design-build contracts, which let costs be negotiated as designs develop. Readers following the bridge should watch the funding and proposal milestones through 2027.

What happens next

Proposals are due March 24, 2027, followed by interviews with proposers from April 12 to 16, 2027.

Further reading

For related coverage, browse Construction news across the region.

Source note: This article includes information reported by Constructionreview.