Spokane Airport Closes Main Curbside for Renovation

The terminal curbside is closed to vehicles and pedestrians as utility relocation work advances under the TREX expansion program.

Updated on Nov. 24, 2026 in Air Travel

Spokane Airport Closes Main Curbside for Renovation

Spokane International Airport closed a major part of its main terminal curbside to vehicles and pedestrians starting October 21, 2026. All vehicle traffic now runs along a two-lane bypass road, while pedestrians are directed to skybridges.

Why it matters

The closure lets crews relocate water, sewer, and gas utilities as the airport moves through its Terminal Renovation & Expansion (TREX) program. Travelers using the airport can expect a changed arrival and drop-off routine for several years.

The Phase 1 Concourse C Expansion, completed in June 2026, added 144,000 square feet, three gates, and six ticket counters at a cost of $150 million. The Phase 2 Central Hall Project, which is aimed at a 255,000-square-foot centralized facility, has not yet been completed.

The players

Spokane International Airport

The airport serving Spokane, Washington, is midway through its Terminal Renovation & Expansion program and handled about 4.4 million passengers in 2025.

Spokane County

Spokane County is a co-owner of the airport alongside the City of Spokane.

The details

The main terminal curbside was closed to vehicles and pedestrians on October 21, 2026, and the inbound roadway was reduced from three lanes to two. Vehicle traffic is routed along a two-lane bypass road, and pedestrians are directed to skybridges.

Timeline

  1. October 21, 2026: Main terminal curbside closed to vehicles and pedestrians.

  2. February 2027: Temporary Concourse C baggage claim begins and hallway demolition is scheduled.

  3. Early 2027: Utility relocation work is expected to finish.

  4. 2027 to 2030: Central Hall construction is scheduled.

  5. 2030: The curbside bypass arrangement is expected to end.

Travel Outlook

The curbside closure is part of the airport's multiyear TREX program, which is moving from the finished Concourse C expansion into the Central Hall project. The airport's passenger count is projected to rise from about 4.4 million in 2025 to more than 6.2 million by 2030, which puts added pressure on the temporary arrangements.

Travelers should allow extra time for drop-off and pickup, since all vehicle traffic now uses a two-lane bypass road. Pedestrians should follow the signed route to the skybridges rather than the closed curbside.

The takeaway

The curbside changes are temporary but will last until about 2030, so frequent flyers should check the airport's current arrival instructions before each trip. Planning around the bypass road now can prevent delays later.

What happens next

Utility relocation work is expected to finish in early 2027, and the temporary Concourse C baggage claim begins in February 2027. The Central Hall construction runs from 2027 to 2030.

Further reading

For more on how the airport is changing, see Air Travel coverage for Spokane.

Source note: This article includes information reported by Simple Flying.