Shoreline Bridge Over I-5 Delayed to Spring

Installation of the pedestrian bridge over Interstate 5 will not happen on the targeted November 2026 dates after a manufacturing problem was found.

Updated on Nov. 10, 2026 in Air Travel

Steel pedestrian bridge arch spanning a wide highway corridor, with evergreen trees along the embankments under overcast northwest skies.
The City of Shoreline's pedestrian bridge over Interstate 5 will not open on its targeted November 2026 dates after a manufacturing defect was found in one arch. AI Illustration. Upload story photo >

Live Poll

Would you take light rail instead of driving to a game or event?

The City of Shoreline's pedestrian bridge over I-5 will not be installed on its targeted November 2026 dates. The contractor discovered manufacturing issues with one of the bridge arches and is working with the manufacturer to resolve them.

Why it matters

The bridge connects west-side I-5 development to the light rail station just north of NE 145th St., so the delay pushes back a direct pedestrian link to transit in Shoreline. The arch problem also means the schedule depends on how the manufacturer resolves the defect.

The installation required closing I-5 at night to lift the bridge into place, and the targeted nights were Nov. 7 and Nov. 14, 2026. The manufacturer has not yet said whether the arch can be corrected on site or must be replaced.

The players

City of Shoreline

The Washington city government overseeing construction of the pedestrian bridge over I-5 connecting west-side development to light rail.

Sound Transit

The regional transit agency operating Link light rail, including the South Bellevue and Shoreline-area stations served by riders in this story.

The details

The contractor found manufacturing issues with one of the bridge arches and is working with the manufacturer to resolve them. The bridge is expected to open in spring 2027, though construction might have to start over if a new arch is required.

Timeline

  1. Nov. 7 and Nov. 14, 2026: Targeted nights for closing I-5 and installing the bridge.

  2. Monday, Nov. 9, 2026: City of Shoreline issued the delay statement.

  3. Spring 2027: Anticipated opening of the pedestrian bridge.

Travel Outlook

Light rail access near I-5 is tied to the Link line extension to Lynnwood, which already carries heavy game-day ridership. Pedestrian connections like this bridge determine how easily riders reach stations as that network grows.

Riders who rely on the pedestrian bridge to reach light rail should plan around the delay and expect the existing access routes to remain in use into spring 2027. Eastside fans using South Bellevue's 1,500-space park-and-ride should continue to expect game-day boardings of about 3,500 people.

The takeaway

Construction timelines for transit access projects can shift quickly when a single component fails inspection, so riders should check official city and transit updates before planning trips that depend on new routes.

What happens next

The manufacturer's decision on whether the arch can be corrected on site or must be replaced will determine the revised installation schedule, with the bridge expected to open in spring 2027.

Further reading

For more on how riders reach trains around the region, see Air Travel coverage.

Source note: This article includes information reported by My Northwest.