City Closes Pullman River Path for Bridge Work
Pedestrian path along the South Fork Palouse River closes starting November 24, 2026, while crews move a bridge back into place.
Updated on Nov. 24, 2026 in Business

The City of Pullman is closing the pedestrian path along the north side of the South Fork Palouse River beginning November 24, 2026. The closure supports construction on the Pine Street Pedestrian Bridge, which crews will move back into place.
Why it matters
The closure restricts pedestrian access along the river in Pullman for several weeks during the project. Residents and visitors using the path or the nearby parking lot will need to plan alternate routes.
The pedestrian path closure begins November 24, 2026, with construction anticipated to be completed by December 16, 2026. The source does not say whether the schedule could shift due to weather or crane conditions.
The players
City of Pullman
Pullman is a city in Whitman County, Washington, home to Washington State University, and its municipal government manages public infrastructure such as the river path and bridges.
The details
Crews will use a crane to lift the Pine Street Pedestrian Bridge back into position, and both the pedestrian path and the parking lot behind Via Chiropractic will be closed during crane operations. The path will remain closed until all construction work is finished.
Timeline
November 24, 2026: Pedestrian path closure begins.
December 7-11, 2026: Crane moves the bridge; path and parking lot closed.
December 14-16, 2026: Bridge underside repairs and surrounding area work.
Construction Pattern
Crane-based bridge repositioning on municipal pedestrian crossings typically requires short, scheduled closures of adjacent paths and parking so that lifting operations can proceed safely. The Pullman project follows that common approach for work on the Pine Street Pedestrian Bridge.
Pedestrians who normally use the river path should plan alternate routes beginning November 24, 2026. Visitors to Via Chiropractic should expect the adjacent parking lot to be unavailable during crane operations in early December.
The takeaway
Plan around the closure well ahead of time, since the path and nearby parking will be unavailable for roughly three weeks. Checking the city's updates before traveling the route can help avoid last-minute detours.
What happens next
Crews are scheduled to finish construction by December 16, 2026, at which point the pedestrian path and parking lot are expected to reopen.