Columbia River Contractors Is Sole Bidder
A single joint venture responded to the state's request for qualifications on the $14.4 billion Interstate 5 Bridge replacement.
Updated on Nov. 18, 2026 in Construction

Live Poll
Do you trust local governments to deliver big infrastructure projects well?
Columbia River Contractors, a joint venture of Kiewit Infrastructure West, Guy F. Atkinson Construction, and Traylor Bros. Inc., was the only company to respond to the program's request for qualifications for the Interstate 5 Bridge replacement, estimated at $14.4 billion. The roughly five-mile project crosses the Columbia River between Oregon and Washington and includes a light rail extension into Vancouver.
Why it matters
With only one qualified respondent, the procurement is at its next gate and competitive pricing pressure on the project is uncertain. The leadership reorganization comes as the project nears delivery, positioning the program for its next phase in Washington and Oregon.
The joint venture is the sole respondent to the request for qualifications for a $14.4 billion, five-mile bridge replacement. Whether any other firm will bid once the request for proposals is released on November 23 has not been determined.
The players
Columbia River Contractors
A joint venture of Kiewit Infrastructure West, Guy F. Atkinson Construction, and Traylor Bros. Inc. that is the sole respondent to the bridge procurement.
Ron Paananen
A former Washington State Department of Transportation programme administrator with 21 years of megaprogramme leadership experience who takes over as permanent administrator.
The details
The joint venture brings together Kiewit Infrastructure West, Guy F. Atkinson Construction, and Traylor Bros. Inc. The procurement advances to its next gate, with the request for proposals scheduled for release on November 23 and contract award expected in 2027.
Timeline
2025 (end of year): The chair position of the administrator became vacant.
November 16, 2026: The Columbian reported the sole joint venture bidder.
November 23, 2026: Request for proposals scheduled for release.
December 2, 2026: Ron Paananen begins as permanent programme administrator.
2027: Contract award expected; construction is expected to start in 2028.
Roadmap
The single response to the Interstate 5 Bridge request for qualifications places the project at the request-for-proposals stage that follows the procurement sequence set by the program. The leadership change at the administrator level comes as the program moves toward a 2027 contract award and 2028 construction start.
Commuters crossing the Columbia River between Washington and Oregon will ultimately see the existing bridge replaced and light rail extended into Vancouver. Construction is not expected to begin until 2028, so near-term travel conditions are not affected by this procurement news.
The takeaway
A single qualified bidder can signal limited competition, so the upcoming request for proposals will show whether additional firms enter the bidding for this major crossing.
What happens next
The request for proposals is scheduled for release on November 23, 2026, and contract award is expected in 2027.
Further reading
Explore more on Construction projects across the region.
Source note: This article includes information reported by Constructionreview.
Live Poll
Do you trust local governments to deliver big infrastructure projects well?