Asbestos Delays Richmond School Demolition
Crews found asbestos in the old Richmond High School of the Arts, pushing the second phase of demolition into summer 2028.
Updated on Nov. 10, 2026 in Home Renovation

Live Poll
Do you trust your local government to manage school construction costs well?
Crews uncovered a significant amount of asbestos encased in the walls of the old Richmond High School of the Arts during demolition. Richmond Public Schools requires removal before demolition can move forward, adding between $3 million and $5 million to the project cost.
Why it matters
The added cost and delay affect how the city's school facilities projects are funded and scheduled. The removal is labor-intensive and must be completed before the remaining demolition can continue.
The asbestos removal adds $3 million to $5 million to demolition costs, according to the school division. The estimated four-to-seven-month delay has not been finalized, and the full revised budget is still pending.
The players
Richmond Public Schools
The city's public school division, which oversees the school's demolition and is responsible for the project budget and timeline.
The details
Asbestos was found encased in the walls during demolition of the old Richmond High School of the Arts. Removal must happen before demolition can continue, a process that officials describe as labor-intensive.
Timeline
Fall 2027: original expected completion of the second demolition phase.
Summer 2028: tentative new completion date for the second demolition phase.
Tuesday: information on the revised plan will be presented at the next Richmond school board meeting.
Home Renovation Context
Richmond voters approved a 1% sales tax increase earmarked for capital projects, and the added asbestos cost now draws on that same capital funding stream. The overrun shows how older building materials can reshape the budgets of public renovation work.
The added cost could affect how the district allocates capital funds for other school and city projects. Residents who voted for the sales tax increase may see the money stretched further as these costs are absorbed.
The takeaway
Older buildings can hide hazardous materials like asbestos that significantly increase renovation costs and timelines. Planning for contingencies in capital budgets can help absorb unexpected expenses.
What happens next
The revised demolition plan and cost estimate are expected to be presented at the next Richmond school board meeting on Tuesday.
Further reading
Explore more on Home Renovation to see how older building materials affect renovation budgets.
Source note: This article includes information reported by WRLH.