Charlottesville Dewberry Hotel Property Has Been Contracted
The unfinished Water Street hotel site is under contract following a city ultimatum regarding its future.
Updated on Sept. 25, 2026 in Hotels

Live Poll
Should cities impose strict deadlines on developers for unfinished property projects in your area?
The Dewberry hotel property at 201 E. Water St. is now under contract after the City of Charlottesville issued a 60-day ultimatum. Officials demanded the owner provide a concrete plan to complete construction, sell, or demolish the long-stalled concrete and steel frame.
Why it matters
The site has remained an unfinished structure without basic building services for years, prompting local authorities to force a resolution. The city has explicitly stated it maintains no financial support agreements for the property, shifting the burden of completion or removal entirely to the developer.
The property at 201 E. Water St. was purchased at a public auction for $6.25 million in 2012. The developer now has 60 days to finalize a plan for the unfinished site following the city's recent demand.
The players
John Dewberry
He is the owner of the hotel property through his firm, Deerfield Square Associates II, LLC.
City of Charlottesville
The local government authority that issued demands to the developer regarding the future of the Water Street property.
The details
The project remains an empty shell of concrete and steel that lacks essential utilities or interior finishes. This recent contract follows a pair of letters sent by the city in August and September 2026 requiring the owner to decide the path forward for the vacant structure.
Timeline
2010: The Dewberry hotel in Charleston opened.
2012: The developer purchased the Charlottesville site at auction.
2017: A previous property agreement was brokered by a former mayor.
August 19, 2026: The city sent an initial letter demanding a development plan.
September 23, 2026: A follow-up reminder letter was issued to the developer.
Roadmap
This development reflects the ongoing struggles of stalled urban hospitality projects in mid-sized markets. It marks a significant shift from the 2017 property agreement, which failed to yield a finished hotel or successfully leverage the site for local tourism growth.
Residents and visitors to the downtown area may see progress on the long-vacant site once the new contract moves forward. The resolution of this project could finally remove a significant eyesore from the city center that has persisted for over a decade.
The takeaway
The move to put the property under contract suggests the long-running dispute over the unfinished site is nearing a resolution. Property owners should note that local authorities are increasingly utilizing formal ultimatums to address stalled urban development projects.
Further reading
For more information on ongoing hospitality projects in the area, visit the Charlottesville Hotels section.
Source note: This article includes information reported by Cville Right Now - Charlottesville VA's News, Sports & Weather.