Utah Trust Lands Administration board refused a request to reconsider its ground lease to Valar Atomics for a Carbon County nuclear reactor and data center project. The Carbon County planning commission separately approved a permit for Valar's Raceway Energy Campus without a public hearing.
Why it matters
Valar plans to produce 9.6 gigawatts of power through hundreds of small nuclear reactors, a output compared against Utah's roughly 3.5 million residents. Nearby residents, including members of one family living near Wellington, say they were not given a meaningful chance to weigh in before key approvals were granted.
Valar plans 9.6 gigawatts of output from hundreds of small reactors, while residents were limited to two and a half minutes each during the Zoom public comment period. The Bureau of Land Management is only in the early stage of reviewing the company's separate federal application.
The players
Valar Atomics
A nuclear technology company developing small modular reactors and a data center campus in Carbon County, Utah.
Utah Trust Lands Administration
The Utah state agency that manages school and institutional trust lands and issues long-term ground leases, including the Valar lease.
U.S. Bureau of Land Management
The federal agency that oversees public lands and is reviewing Valar's land use application and will conduct any required environmental analysis.
The details
The Utah Trust Lands Administration approved Valar's ground lease two months before a residents' reconsideration request on November 19, 2026, and did not place the project on its Thursday agenda. The board said a signed lease is a legally binding contract that cannot be reconsidered, while Carbon County Attorney Christian Bryner told attendees the planning commission was not required to hold a public hearing on Valar's permit.
Timeline
August 2026: Utah Trust Lands Administration held its first public meeting on the Valar project.
September 2026: A second public meeting was held, and Valar told NPR it had spent eighteen months answering neighbors' questions.
Two months before November 20, 2026: The Trust Lands board approved the Valar ground lease.
Last week before November 20, 2026: Carbon County planning commission approved the Raceway Energy Campus permit without a public hearing.
November 19, 2026: Residents asked the board to reconsider the lease.
Roadmap
Valar's project will be judged first by the federal environmental review that the Bureau of Land Management must start under the National Environmental Policy Act if it accepts the application. Utah's state lease and county permit approvals come before that review, so the sequence of approvals is itself becoming a point of contention for nearby residents.
Residents near Wellington face a large industrial nuclear and data center project approved without a public hearing at the county level, leaving them limited formal channels to contest it. The state lease is treated as a binding contract, so the main remaining opportunity for public input is the federal environmental review.
The takeaway
Approval of a project often happens in stages, and public input may be most effective at the stage where decisions are still open, such as federal environmental review. Residents tracking similar projects should check which agency holds the next decision and when its comment period opens.
What happens next
If the U.S. Bureau of Land Management accepts Valar's application and deems it complete, it will begin an environmental analysis required under federal law.
Further reading
For more on the infrastructure behind this project, see Data Centers coverage across Utah.
Source note: This article includes information reported by KPVI.
Live Poll
Do you trust your local government to give residents a real say on major projects?