Waco ISD Athletics Upgrades Projected at $8.9 Million
Trustees have approved $6.2 million in unspent 2021 bond funds, but took no action on the latest cost report.
Updated on Nov. 24, 2026 in Education

Live Poll
Do you trust your local school district to manage bond money well?
Waco Independent School District's engineer projected about $8.9 million in athletics upgrades at University High School and Cesar Chavez Middle School, roughly $3 million above the earmarked budget. Trustees took no action on the report at Thursday's meeting.
Why it matters
The upgrades are meant to bring athletic facilities at both schools in line with those at the new Waco High School, G.W. Carver Middle School, and Tennyson Middle School. They are also intended to let the district's middle schools host games, easing scheduling and transportation problems for Waco families.
The projected $8.9 million total compares with $6.2 million in unspent funds from the $355 million 2021 bond issue, leaving roughly $3 million unfunded. Alternates would raise the University High project to $7.6 million and the Cesar Chavez project to $1.3 million, and trustees have not yet decided which options to pursue.
The players
Waco Independent School District
The public school district serving Waco, Texas, whose board of trustees oversees the 2021 bond program and the athletics upgrades.
Walker Partners
The architecture and engineering firm that prepared the cost estimate presented to the Waco ISD board.
Oncor Electric Delivery
The regulated electricity transmission and distribution utility serving North Texas, which would assume maintenance responsibility for a relocated power supply at Cesar Chavez Middle School.
The details
The University High project includes a synthetic turf field, new and repaired tennis courts, and a reconditioned track, while Cesar Chavez would receive a resodded football field, irrigation system, and resurfaced track. Engineers noted that soil weakness at the University High field requires significant modification to support turf, and that the Cesar Chavez track needs a mill and overlay process.
Timeline
2021: Voters approved the $355 million Waco ISD bond issue.
Thursday: The engineer presented the cost estimate at the board meeting, and trustees took no action.
February: Construction could begin, barring permitting delays.
July: The turf field could be ready for the start of football practice.
August: Athletics projects could be completed.
Industry Dynamics
The athletics package draws on the $355 million 2021 Waco ISD bond approval, which voters endorsed for facility needs across the district. Its $6.2 million reallocation shows how remaining bond balances are being redirected toward athletic facilities that trail newer campuses in the district.
Families with students at University High and Cesar Chavez may see field and track work begin as early as February, with turf potentially ready by July for football practice. Shifting utility maintenance and possible alternate scope decisions could also affect whether the full package is delivered on schedule.
The takeaway
Because the projected cost exceeds the remaining bond balance, the district's next decisions on alternates and funding will determine which athletics upgrades Waco students actually receive. Parents and community members can track future trustee meetings for those choices.
Further reading
For more on how local districts plan and fund school facilities, explore Secondary Education coverage across Waco.
Source note: This article includes information reported by Waco Tribune-Herald.