Waco Awards Contract for Riverside Lift Station Upgrade
The city council approved a $1.32 million project to expand sewage capacity near major housing developments.
Updated on Oct. 29, 2026 in Home Renovation

Live Poll
Do you support prioritizing public utility upgrades to facilitate new residential developments in your area?
The Waco City Council has awarded a $1.32 million contract to Quality W Contractors LLC to upgrade the aging Riverside Lift Station. This project will significantly boost the facility's wastewater handling capacity to support ongoing residential growth in the region.
Why it matters
The upgrade is essential to accommodate the increased sewage load from planned housing developments. By expanding infrastructure capacity, the city ensures that future residents have reliable utility services in areas where gravity alone cannot move wastewater.
The Riverside Lift Station will increase capacity from 475 to 1,750 gallons per minute following the $1.32 million project. Quality W Contractors LLC secured the deal after submitting the lowest bid among 10 applicants.
The players
Waco City Council
This local government body manages municipal operations and approves infrastructure spending for the city.
Quality W Contractors LLC
This firm is the designated contractor responsible for the construction and mechanical upgrades at the lift station.
Walker Partners
This engineering and consulting firm is tasked with providing construction-phase services, administration, and site layout oversight.
The details
The renovation encompasses extensive site improvements, including new piping, electrical systems, and the relocation of generators. Additionally, the council approved an extra $125,286 for construction-phase services, bringing the total contract for partner firm Walker Partners to $1.05 million.
Timeline
The Riverside Lift Station was originally built in 2006.
The city council approved the design agreement with Walker Partners in September 2023.
The contract was awarded to Quality W Contractors on October 20, 2026.
Construction is expected to begin in November 2026.
The project is expected to reach completion by October 2027.
Culture Shift
This project aligns with the city of Waco's long-term utility capacity planning as municipal infrastructure struggles to keep pace with rapid residential expansion. It reflects a broader trend of cities modernizing legacy systems to accommodate sustained suburban growth.
Residents in the vicinity of the Riverside Lift Station may notice increased construction activity and site work starting in November 2026. These upgrades ensure long-term service reliability for the area as new housing subdivisions continue to develop.
The takeaway
Reliable sewage infrastructure is a prerequisite for neighborhood development and long-term property viability. Property owners in growing areas should monitor city planning updates to stay informed about utility capacity projects that support community expansion.
What happens next
Construction is slated to begin in November 2026, with the total project duration expected to last 11 months until completion in October 2027.
Further reading
Learn more about local improvement projects in the Waco Home Renovation section.
Source note: This article includes information reported by Waco Tribune-Herald.