Tyler Council Approves $469,000 in Culvert Engineering

Two engineering contracts with Elledge Engineering Corp. will advance drainage repairs at Hillside Park, Saunders Avenue and High Avenue.

Updated on Nov. 18, 2026 in Lifestyle

Vector editorial illustration of a large concrete culvert set into a red clay embankment beside a flowing creek, illustrating drainage infrastructure work.
Tyler City Council approved $469,000 in engineering contracts with Elledge Engineering Corp. to repair drainage culverts at Hillside Park, Saunders Avenue and High Avenue. AI Illustration. Upload story photo >

Tyler City Council approved two engineering work orders totaling $469,000 with Elledge Engineering Corp. The projects are funded through the 2027 Half Cent Sales Tax Annual Work Program.

Why it matters

The existing culverts at Saunders Avenue and High Avenue are too small to adequately handle local drainage, and the Hillside Park culvert is aging. The engineering work prepares both projects to move toward construction in Tyler.

The approvals total $469,000, with $180,000 for Hillside Park and $289,000 for Saunders Avenue and High Avenue. Construction timing for the Saunders and High Avenue work was not specified in the approval.

The players

Elledge Engineering Corp.

Elledge Engineering Corp. is a small engineering firm selected by the City of Tyler for the two drainage design work orders.

The details

The Hillside Park work will replace about 200 feet of the concrete top, repair eroded areas, and reseal the culvert bottom, while adding a new junction to increase drainage capacity. The Saunders Avenue and High Avenue project will replace undersized culverts with properly sized ones and raise portions of the roadway to help water move more effectively.

Timeline

  1. Wednesday (before November 18, 2026): Council approved the two engineering work orders.

  2. 2027: Both projects are included in the 2027 Half Cent Sales Tax Annual Work Program.

  3. Summer 2027: Estimated start of Hillside Park culvert construction.

Roadmap

The approvals move two drainage projects funded by the 2027 Half Cent Sales Tax Annual Work Program from planning toward construction. They reflect the city's use of dedicated sales tax revenue to address aging and undersized infrastructure.

Residents near Saunders Avenue and High Avenue should see improved drainage once the undersized culverts are replaced. Drivers on the raised roadway sections may experience better water runoff during heavy rain.

The takeaway

Aging drainage infrastructure is being addressed through planned, funded engineering work rather than emergency repairs. Tyler residents can track the 2027 Half Cent Sales Tax work program for upcoming project timelines.

What happens next

Construction at Hillside Park is estimated to begin in summer 2027, following completion of the engineering work.