VIA Reconfigures San Pedro Avenue for Green Line
Construction along San Pedro Avenue near North Star Mall is reducing traffic to a single lane in each direction as bus rapid transit lanes are built.
Updated on Nov. 8, 2026 in Construction

Live Poll
Do you support major road construction if it brings new local bus lanes?
VIA Metropolitan Transit is reconfiguring San Pedro Avenue for the Green Line bus rapid transit, and much of the corridor has been reduced to a single lane in each direction. Drivers near North Star Mall have reported chaotic conditions as they navigate barrier walls, fencing and detours.
Why it matters
The roadwork is needed so VIA can reconfigure the road to accommodate bus lanes along the corridor. Once complete, buses will travel north and south along San Pedro Avenue, changing how residents move through the area.
VIA has divided the corridor's construction tasks into 12 segments to minimize delays. Segment 11 includes the detours in the area shown in a viral video, and the source does not provide a timeline for completing each segment.
The players
VIA Metropolitan Transit
VIA Metropolitan Transit is the public transportation agency serving San Antonio, Texas, and is responsible for the Green Line bus rapid transit project.
The details
Drivers are being forced around barrier walls and white and orange fencing while the road is reconfigured. A TikTok video posted November 2, 2026 described the stretch between Oblate Drive and Loop 410 as a 'bike rodeo.'
Timeline
Monday, November 2, 2026: A TikTok video describing the San Pedro roadwork as a 'bike rodeo' is posted.
2028: The VIA Green Line bus rapid transit is expected to be completed on San Pedro Avenue.
Roadmap
The San Pedro Avenue reconstruction is an active phase of VIA's Green Line bus rapid transit project, which is expected to be completed in 2028. The current lane reductions show the project moving from planning into physical reconstruction of the corridor.
Drivers on San Pedro Avenue near North Star Mall should expect single-lane traffic in each direction and detours around barrier walls and fencing while the work continues. Commuters using the corridor will face these conditions until the bus lanes are completed in 2028.
The takeaway
Commuters on San Pedro Avenue should plan extra travel time while the corridor is reduced to a single lane in each direction. The completed Green Line will change how buses move along this stretch of San Antonio.
Further reading
For more on local building projects, see San Antonio Construction.
Source note: This article includes information reported by MySA.
Live Poll
Do you support major road construction if it brings new local bus lanes?