EPA Proposes New Limits for Port Arthur PCB Incinerator
The EPA is seeking public comment on modified operating requirements for the Veolia facility in Port Arthur.
Updated on Oct. 27, 2026 in Electric Vehicles

Live Poll
Should federal regulators impose stricter operating limits on local industrial hazardous waste incinerators?
The EPA has proposed new interim operating limits for the Veolia ES Technical Solutions PCB incinerator in Port Arthur. The federal agency is now accepting public feedback for a 30-day period.
Why it matters
The proposed modifications follow a request from Veolia to adjust operating parameters for the incinerator. These changes will remain in effect until the company completes a trial burn scheduled for 2027.
The EPA has proposed an interim kiln exit temperature of 1,443°F and a maximum stack gas flow of 35,350 dry standard cubic feet per minute. Additionally, the proposal sets a minimum temperature of 2,012°F for the secondary combustion chamber.
The players
Environmental Protection Agency
The federal agency responsible for regulating industrial environmental impacts and overseeing the Toxic Substances Control Act.
Veolia ES Technical Solutions
An environmental services company that operates the hazardous waste incineration facility located in Port Arthur.
The details
The agency initiated this regulatory update under the Toxic Substances Control Act to replace existing requirements. The adjustments will govern the facility's operations leading up to a mandatory destruction and removal efficiency test set for September 2027.
Timeline
April 1, 2025: The EPA approved the 2025 trial burn plan.
June 30, 2026: Veolia submitted a request for changes to operating limits.
October 26, 2026: The EPA proposed modifications to the facility approval.
November 26, 2026: The public comment period for docket EPA-R06-RCRA-2026-9274 is scheduled to close.
September 2027: A new trial burn for the incinerator is scheduled to occur.
Roadmap
This regulatory update reflects the ongoing oversight of legacy industrial disposal technologies within the broader chemical waste sector. It highlights the stringent operational adjustments required for facilities navigating shifting federal environmental compliance standards.
Residents of Port Arthur can participate in the formal review process by submitting comments on the proposed changes before the November 26, 2026 deadline. This engagement serves as the primary mechanism for the public to address operational concerns regarding the site.
The takeaway
The EPA is moving forward with an updated regulatory framework for the Port Arthur facility ahead of its 2027 testing cycle. Stakeholders should note that these interim requirements are intended to bridge the period before final performance data is collected.
Further reading
For broader updates on regional environmental policy, explore the Electric Vehicles section.
Source note: This article includes information reported by Environment+Energy Leader.