Odessa to Reconstruct East 52nd Street in 2027

The $4.7 million project will rebuild the roadway between North Grandview Avenue and North JBS Parkway in four phases.

Updated on Nov. 25, 2026 in Industry

Wide photo of a partially closed road under construction, with orange barrels guiding traffic into one lane, a parked paving machine, and flat open terrain beyond.
The City of Odessa will rebuild East 52nd Street between North Grandview Avenue and North JBS Parkway in four phases, starting January 4, 2027, at a cost of $4.7 million. AI Illustration. Upload story photo >

Live Poll

Do you think major road construction in your area is worth the disruption?

The City of Odessa will reconstruct East 52nd Street from North Grandview Avenue to North JBS Parkway, a $4.7 million project to be completed in four phases. Construction is expected to begin on January 4, 2027, with completion projected for September 2027.

Why it matters

The phased approach is designed to keep traffic moving, with one eastbound and one westbound lane expected to remain open for most of the work. Residents who commute along the corridor should expect shifting traffic patterns as crews move between sections of the roadway.

The reconstruction carries a total budget of $4.7 million and will be carried out in four phases, with one eastbound and one westbound lane generally kept open. The extraction does not state how the phase schedule or costs may shift if the start date changes.

The players

City of Odessa Engineering Department

The municipal department responsible for planning, overseeing and fielding public questions about city infrastructure projects such as road reconstruction.

Jones Bros. Dirt and Paving Contractors

A local dirt and paving contractor listed as the point of contact for questions about the East 52nd Street project.

The details

The project covers East 52nd Street from North Grandview Avenue to North JBS Parkway and begins with the segment between North Grandview Avenue and North Tanglewood Lane before moving east. Work will alternate between the southern and northern halves of the roadway, with temporary lane adjustments, construction barriers, and signage placed as traffic patterns change.

Timeline

  1. December 1: Town hall meeting on the project at 5:30 p.m. at the Complex Community Federal Credit Union Training center, 4519 East 51st Street.

  2. January 4, 2027: Expected start of construction.

  3. September 2027: Expected completion of construction.

Market Landscape

The East 52nd Street project follows the phased reconstruction pattern Odessa has used on its major arterial corridors, dividing a single roadway into sequenced segments rather than closing it all at once. The approach reflects a municipal strategy of keeping at least one lane in each direction open while contractors rebuild the road in sections.

Drivers using East 52nd Street should plan for lane shifts, barriers and signage once work begins in early 2027. Residents can raise questions about the project at the December 1 town hall meeting or contact the City of Odessa Engineering Department.

The takeaway

Drivers who travel East 52nd Street regularly should monitor city announcements in late 2026 and early 2027 for updated traffic plans before construction starts. Attending the December 1 town hall meeting is one direct way to ask about phase timing and detours.

What happens next

Construction is expected to begin on January 4, 2027, and to be completed in September 2027, with the first phase running between North Grandview Avenue and North Tanglewood Lane.

Further reading

For more on local building work, explore the Construction coverage for Odessa.

Source note: This article includes information reported by Odessa American.

Live Poll

Do you think major road construction in your area is worth the disruption?