STN One Outlines AI Data Center Model in Odessa
The Texas developer detailed an integrated business model for its Project Landman campus in Ector County, where its first 2 MW unit is already operating.
Updated on Nov. 12, 2026 in Data Centers

Live Poll
Do you think new AI data centers will be good for your community?
STN One outlined an integrated AI data center business model on November 11, 2026, tied to its Project Landman campus in Odessa, Texas. The company commissioned its first 2 MW Elemental Data Center unit at the site on July 31, 2026.
Why it matters
The campus is designed to scale from an initial 400 MW deployment to 1.6 GW, making it a significant addition to computing infrastructure for Odessa and Ector County. Its development supports 375 jobs now, with 200 permanent positions expected as operations expand.
The first factory-built unit is designed for 2 MW of computing capacity and can hold 1,024 NVIDIA Blackwell Ultra B300 GPUs, or 1,008 GB300 GPUs if reconfigured. The company has not identified its generation technology, on-site generating capacity, or battery storage size.
The players
STN One Incorporated
STN One is the developer of the Project Landman AI data center campus in Odessa, Texas, and is pursuing an integrated model that pairs modular data center manufacturing with enterprise AI agents for infrastructure management.
Ector County Commissioners' Court
The Ector County commissioners' court is the local governing body that scheduled a presentation on Project Landman and will consider authorizing county officials to sign related documents.
The details
STN One manufactures modular data center facilities to its own specifications and installs essential operating systems before delivery, with module production and site preparation running simultaneously. The campus combines on-site power generation and battery storage with a utility connection, and uses sealed, closed-loop cooling with no process water discharge.
Timeline
May 2026: Construction on the Project Landman campus began.
June 11, 2026: First Elemental Data Center was delivered to the Odessa site.
July 31, 2026: The first 2 MW unit was commissioned.
November 11, 2026: STN One outlined its integrated AI infrastructure business model.
November 12, 2026: Ector County commissioners' court scheduled a Project Landman presentation and consideration of authorizing officials to sign associated documents.
The Tech Race
The Odessa campus is built to host NVIDIA's Blackwell Ultra B300 GPUs and can be reconfigured for the GB300 generation within the same footprint. That design choice reflects how AI infrastructure developers are building modular sites that can keep pace with successive GPU platforms rather than fixed, single-generation facilities.
For Odessa residents, the campus is expected to bring new jobs, with 200 permanent positions anticipated as operations expand beyond the current 375. Ector County residents may see local government action, as commissioners are scheduled to consider authorizing officials to sign Project Landman documents.
The takeaway
The Odessa project shows how AI data center developers are pairing modular manufacturing with on-site power and closed-loop cooling to scale quickly. Local residents should watch for the commissioners' court decision and STN One's disclosures on power sourcing and construction timing.
Further reading
For broader context on how these facilities are being built and powered, see Data Centers coverage in Odessa.
Live Poll
Do you think new AI data centers will be good for your community?






