Killeen Weighs $139K Change Order for Lift Station

The Killeen City Council will consider a $139,215 change order to upgrade a bridge crane at the Lift Station No. 6 rehabilitation project.

Updated on Nov. 30, 2026 in Politics

Killeen Weighs $139K Change Order for Lift Station

Live Poll

Do you support higher water and wastewater fees to fund city infrastructure growth?

The Killeen City Council is set to consider a proposed $139,215 change order for the Lift Station No. 6 rehabilitation at its Tuesday meeting at 5 p.m. The change would replace a single-girder bridge crane with a double-girder crane, raising the construction contract with Bell Contractors Inc. from approximately $6.96 million to $7.1 million.

Why it matters

The Lift Station No. 6 project is designed to raise pumping capacity from 17 million to 24 million gallons per day, a 41% increase for the city's wastewater system. Engineers determined the original crane would restrict certain maintenance procedures inside the facility, so city engineering and public works officials support the change.

The council is scheduled to consider the change order at its Tuesday meeting at 5 p.m. at City Hall, 101 N. College St. The project is anticipated to be completed in April 2027.

The players

Killeen City Council

The Killeen City Council is the governing body of the city of Killeen, Texas, which oversees municipal contracts, budgets and public infrastructure projects.

Bell Contractors Inc.

Bell Contractors Inc. is the construction firm holding the contract to rehabilitate the Lift Station No. 6 wastewater facility in Killeen.

The details

Project engineers with Freese and Nichols found the originally specified single-girder bridge crane would limit maintenance inside the Lift Station No. 6 facility. The proposed double-girder crane provides additional vertical clearance, allowing maintenance personnel to disassemble pumps inside the building.

Timeline

  1. Oct. 21, 2025: The council originally awarded the construction contract.

  2. Q2 2026: The city's capital improvement report listed the project 5% complete.

  3. Tuesday, 5 p.m.: The council is scheduled to consider the change order.

  4. April 2027: The project is anticipated to be completed.

Legal Context

The change order would raise the Bell Contractors Inc. contract from roughly $6.96 million to $7.1 million, following the city's original award of the construction contract on Oct. 21, 2025. The city's second-quarter 2026 capital improvement report listed the project 5% complete and $183,969 in construction payments made to date.

The change order would increase the city's spending on the Lift Station No. 6 project by $139,215 and raise the expanded facility's pumping capacity to 24 million gallons per day. Residents will see the cost and completion timeline tied to this wastewater infrastructure through the council's final vote.

The takeaway

Upgrades to aging wastewater infrastructure often require mid-project design changes, and the council's vote on this change order will determine how the city funds that adjustment. Residents can track the outcome at the Tuesday meeting at City Hall.

What happens next

The council will consider the $139,215 change order at its Tuesday meeting at 5 p.m., and the project is anticipated to be completed in April 2027.

Further reading

For more on how local decisions like this one are made, see the City Hall coverage section.

Source note: This article includes information reported by The Killeen Daily Herald.